Project narrative
In 2020, the Renosterberg Municipality approached Longyuan Mulilo for contributions towards the second phase of their Water Supply Upgrade Project. Longyuan Mulilo agreed to fund the training of municipal staff and to provide remote monitoring equipment for the existing boreholes and reservoirs. The Water Upgrade Project commenced in September 2020, and all parties overcame the challenges and impact of COVID 19 to make the project successful and commissioned it in October 2021. The purpose of this project is to increase water supply for local residents. After completion, the total groundwater abstraction in Philipstown has increased from 6.7 l/sec to 14.3 l/sec, an 113% increase in the original yield.