Skip to content

Overview

China Eximbank provides overseas investment loan for 180MW Asahan-1 Hydroelectric Power Plant Construction Project

Commitments (Constant USD, 2023)$466,426,840
Commitment Year2006Country of ActivityIndonesiaDirect Recipient Country of IncorporationHong Kong (China)SectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Dec 1, 2006
Start (actual)
Jan 29, 2007
End (actual)
Jun 28, 2010
Last repayment (originally scheduled)
Nov 28, 2017

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

More detailed locational information can be found at https://www.openstreetmap.org/way/602689146

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% Chinese ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Joint Venture/Special Purpose Vehicles

  • PT Bajradaya Sentra Nusa (BDSN)

State-owned companies

  • China Huadian Hongkong Company Ltd.

Implementing agencies

State-owned companies

  • China Huadian Engineering Co., Ltd.

Collateral providers

State-owned companies

  • PT Pembangkitan Jawa-Bali (PLN Nusantara Power)

Loan desecription

China Eximbank provides overseas investment loan for 180MW Asahan-1 Hydroelectric Power Plant Construction Project

Grant element8.757%Interest rate (t₀)7.5%Interest typeFixed Interest RateMaturity11 years

Collateral

The 26.05% equity stake of PT Pembangkitan Jawa-Bali pledged its equity stake in the project company [PT Bajradaya Sentra Nusa (BDSN)].

Narrative

Full Description

Project narrative

On December 23, 1996, PT Bajradaya Sentra Nusa (BDSN) — a special purpose vehicle and joint venture — signed a Power Purchase Agreement (PPA) with PT PLN (Persero), the state-owned power utility company in Indonesia, for the 180MW Asahan-1 Hydroelectric Power Plant Construction Project (Asahan-1 HEP). However, due to the Asian Financial Crisis in the late 1990s, construction of the power plant was suspended. BDSN signed an EPC contract with China Huadian Engineering Corporation on March 18, 2004. The EPC contract went into effect on December 31, 2004. However, the project was subsequently put on hold due to financing difficulties. Then, in February 2006, China Huadian Hongkong Ltd. purchased a 70% equity stake in BDSN, which made BDSN a joint venture of China Huadian Hongkong Ltd. [70% equity stake], PT Pembangkitan Jawa-Bali (PLN Nusantara Power) [26.05% equity stake], PT Duta Graha Indah Tbk [3.5% equity stake], and PT Bajradaya Sentranusa [0.45% equity stake]. Shortly thereafter, a project feasibility study was undertaken. Then, in March 2006, China Eximbank issued a letter of intent to China Huadian Hongkong Ltd. regarding its interest in financing the 180MW Asahan-1 Hydroelectric Power Plant Construction Project. Later that year, in August 2006, China Eximbank approved the provision of one or more overseas investment loans for the 180MW Asahan-1 Hydroelectric Power Plant Construction Project. The China Eximbank financing agreements were finalized in December 2006. China Huadian Hongkong Ltd., in turn, on-lent the China Eximbank loan proceeds of the loan to BDSN. A $248,560,000 term loan facility agreement between China Huadian Hongkong Ltd. and BDSN was signed on December 1, 2006. It carried an estimated interest rate of 7.5% and an estimated maturity of 11 years. The borrower was responsible for making 22 semi-annual repayments. PT Pembangkitan Jawa-Bali pledged its equity stake in BDSN as as a source of collateral for China Huadian Hongkong Ltd. The total estimated cost of the 180MW Asahan-1 Hydroelectric Power Plant Construction Project is $359.91 million. It was financed according to a debt-to-equity ratio of 70:30. The purpose of the project was to construct a run-of-river hydroelectric power project — with 2 x 90 MW turbines — in North Sumatera Province in Indonesia. The power plant uses the existing flow of Asahan River to produce electricity and it has no large scale dam or reservoir build for the project, as it is a run-of-river hydroelectric power plant. It takes advantage of Asahan River flow that receives water from its natural source, Lake Toba. Geographically, the power plant is located downstream of Lake Toba and upstream of the existing Asahan 2 (Siguragura) hydroelectric power plant, a large dam power plant built in 1981. The objective of the project was to supply zero emission energy to Sumatera Grid, a grid with relatively carbon-intensive electricity supply that is located in Sumatera island and that had no interconnection with the grid in other islands (e.g. Java, Kalimantan). Upon completion, the project was expected to achieve power production of 1,175,000 MWh per annum to be delivered to PLN and 100,000 MWh per annum as secondary electricity generation. China Huadian Engineering Corporation (CHEC) served as the engineering, procurement and construction (EPC) contractor responsible for project implementation. Construction began on January 29, 2007. The power plant officially commissioned on June 28, 2010.

Staff comments

“1. The Chinese project title is 印尼阿萨汉水电站项目 or Asahan-1水电站项目. 2. 中国对外投资项目案例分析———中国进出口银行海外投资项目精选 is a particularly valuable source of information about this transaction (http://www.wenqujingdian.com/Public/editor/attached/file/20180725/20180725161843_43840.pdf). 3. The face value of the China Eximbank overseas investment loan is unknown. However, China Eximbank M&A (overseas investment) loans typically cover at least 70% of the total cost of the investment. See slide 13 of https://www.dropbox.com/scl/fi/l59pewju61dhll79k8msy/2.EXIM-Bank.pptx?rlkey=4ffouewoknm33jnz3dykii2i4&dl=0 for more information on the standard terms and conditions that govern M&A (overseas investment) loans from China Eximbank. 4. The estimated borrowing terms are drawn from pg. 16 of https://cdm.unfccc.int/UserManagement/FileStorage/U0LWQZYCOVK1ATP73XFEG6D89SMBIH. 5. PT PLN Nusantara Power is a wholly owned subsidiary of PT PLN (Persero), the state-owned power utility company in Indonesia.