China Eximbank contributes to $150 million syndicated loan for Advanced Smart Metering Infrastructure PPP Project

Commitments (Constant USD, 2023)$50,000,000
Commitment Year2023Country of ActivityIndonesiaDirect Recipient Country of IncorporationChina (People's Republic of)SectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jun 9, 2023
Start (actual)
Jan 1, 2023
End (actual)
Jan 9, 2024
Last repayment (originally scheduled)
Jun 7, 2028

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% Chinese ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Cofinancing agencies

Private Sector

  • DBS Bank Ltd.

State-owned Commercial Banks

  • Bank of China (BOC)

Receiving agencies

State-owned companies

  • State Grid Corporation of China (SGCC)

Implementing agencies

State-owned companies

  • State Grid Corporation of China (SGCC)

Insurance providers

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Collateral providers

State-owned companies

  • State Grid Corporation of China (SGCC)

Loan description

BOC and China Eximbank contributions to $150 million syndicated loan for Advanced Smart Metering Infrastructure PPP Project in Indonesia 2023

Interest typeUnknownMaturity5 years

Collateral

The fixed amount due from state-owned utility Perusahaan Listrik Negara (PLN) to SGCC and hard assets.

Narrative

Full Description

Project narrative

On June 9, 2023, the State Grid Corporation of China (SGCC) signed a $150 million syndicated loan agreement with China Eximbank, Bank of China, and DBS Bank. Each bank contributed $50 million. The loan carries a 5-year maturity. Its other borrowing terms of the loan are unknown. However, it is known that the loan is backed by a Sinosure credit insurance policy. It is also known that the borrower was expected to use the proceeds of the loan to finance an advanced metering infrastructure managed services procurement contract between the Indonesian state-owned utility Perusahaan Listrik Negara (PLN) and SGCC, which was signed in December 2022. The public-private partnership (PPP) project was undertaken according to a Build-Own-Operate-Transfer (BOOT) model with a 10-year concession period. Under the concession (BOOT) agreement, SGCC was responsible for the project financing, system design, smart meter terminal and master station system development, site survey, procurement, installation, testing, and commissioning. PLN was responsible for paying a fixed amount to SGCC for its services. The syndicated loan was collateralized against the fixed amount due from PLN and hard assets. The purpose of the project was the installation of up to 1.2 million smart meters in eight provinces (North Sumatra, Banten, Greater Jakarta, West Java, Central Java, East Java, Bali, and Southeast and West Sulawesi) of Indonesia. The smart meters were expected to increase the accuracy of electricity bills on recording meters in each transaction. Construction began in January 2023. Within six months, 14,000 smart meters had been put into operation. By October 2023, 93.54% of the 1.2 million meters had been installed. The entire metering system was put into operation on January 9, 2024.

Staff comments

1. This project is also known as the SGCC Indonesian Advanced Smart Metering Infrastructure PPP Project. 2. Ashurst served as legal counsel to the lenders. King & Wood Mallesons served as legal counsel to the project sponsor. 3. The Chinese project title is 印尼高级智能计量系统项目.