China Eximbank provides RMB 100 million loan for 1522 Low Cost Housing Units Project

Commitments (Constant USD, 2023)$27,891,507
Commitment Year2002Country of ActivityMauritiusDirect Recipient Country of IncorporationMauritiusSectorOther Social Infrastructure And ServicesFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2002
Start (actual)
Jun 26, 2002
End (actual)
Jun 1, 2006
First repayment
Dec 31, 2005
Last repayment
Dec 29, 2013

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

State-owned Banks

  • Development Bank of Mauritius Limited (DBM)

State-owned companies

  • National Housing Development Company Ltd, State-Owned Company

Implementing agencies

State-owned companies

  • China Jiangsu International Economic and Technical Cooperation Company

Loan desecription

China Eximbank provides RMB 100 million loan for 1522 Low Cost Housing Units Project

Grace period4 yearsGrant element30.7323%Interest rate (t₀)4%Interest typeFixed Interest RateMaturity12 years

Narrative

Full Description

Project narrative

On June 19, 2002, the Export-Import Bank of China signed an RMB 100 million loan agreement with the Development Bank of Mauritius Ltd (DBM) for the 1522 Low Cost Housing Units Project. This loan carried the following terms: a 12 year maturity, a 4 year grace period, and a 4% interest rate. DBM used the proceeds from this loan to on-lend to National Housing Development Company Ltd, a state-owned enterprise in Mauritius. This project involved the construction of 1,522 low-income housing units and related facilities. China's Jiangsu International Economic and Technological Cooperation Company was the contractor responsible for implementation. Construction began in 2002 and this project reached completion in 2006. According to a Statement of Contingent Liabilities published by the Government of Mauritius on December 31, 2009, the outstanding balance of this loan was RMB 62.5 million, signifying that repayment had begun by the end of 2009.

Staff comments

This project is also known as the 1522 Low Cost Housing Project, 1522 Low Cost Housing Project, 1522 Low-Cost Housing Project, 1500 Low Cost Housing Project, 1500 Low-Cost Housing Project, the Social Housing Project, and the Low-Cost Housing Construction - 1500 Units Project. The Chinese project title is 成1500套低造价住房 or 1500套低造价住房 or 毛里求斯住房项目 or 毛里求斯1500套住房项目.