Chinese Government provides $10 million USD grant for Phase 1 of Sino-Guinean Friendship Hospital Construction Project (Linked to #64425)

Commitment amount

$ 15245859.21949051

Adjusted commitment amount

$ 15245859.22

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Guinea

Sector

Health (Code: 120)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2008-01-01

Actual start

2009-03-31

Actual complete

2010-07-25

Geography

Description

In 2008, the Chinese Government agreed to provide a $10 million USD grant to the Government of Guinea for Phase 1 of the Sino-Guinean Friendship Hospital Construction Project. This project involved the construction of a 120-bed, “Class A” specialist hospital with cardiology, neurology, radiology, acupuncture and rehabilitation, thoracic surgery, therapeutic surgery, orthopedics, general surgery, brain tumor surgery, emergency, and resuscitation units as well as housing of Chinese medical teams. On April 28, 2008, representatives from a Chinese design firm and the Guinea Ministry of Health had a preliminary design meeting in Wuhan for this hospital. Sichuan Huashi Overseas Investment & Engineering Co., LTD was the contractor responsible for implementation. Construction began on March 31, 2009 and ended on July 25, 2010. The first phase of the project was then officially handed over to the local authorities on April 13, 2011. Then, in 2017, the Chinese Government provided an RMB 100 million grant for Phase 2 of the Sino-Guinean Friendship Hospital Construction Project (#64425). Phase 2 involved the construction of several surgical and intensive care units and well as the provision and installation of medical equipment, such as Magnetic Resonance Imaging (MRI) scanners. Sinohydro Bureau 3 Co. Ltd. was the contractor responsible for implementation. Construction began on November 1, 2018 and an official groundbreaking ceremony took place on December 7, 2018. The originally expected completion date was April 30, 2020. However, it is unclear if Phase 2 has reached completion. As of November 28, 2019, the project had achieved a 70% completion rate. The project may have experienced delays because of the COVID-19 pandemic.

Additional details

The Chinese project title is 几内亚医院项目 or 援几内亚综合医院项目 or 中几友好医院 or 援几内亚给贝医院项目. The French project title is Hôpital De L'amitié Sino-Guinéen De Kipé.

Number of official sources

30

Number of total sources

41

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Guinea [Government Agency]

Implementing agencies [Type]

Sichuan Huashi Group Corporation Limited [Private Sector]

Guinea Ministry of Health and Public Hygiene [Government Agency]