Project ID: 1464

China Eximbank provides RMB 634 million government concessional loan for Phase 3 of Addis Ababa Deep Wells Water Supply Project

Commitment amount

$ 120618294.57667074

Adjusted commitment amount

$ 120618294.58

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Ethiopia

Sector

Water supply and sanitation (Code: 140)

Flow type

Loan

Level of public liability

Central government debt

Financial distress

Yes

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2011-08-16

Actual start

2012-11-19

Actual complete

2015-03-08

Geography

Description

On August 16, 2011, China Eximbank and the Government of Ethiopia signed an RMB 634 million ($95,680,000 or ETB 1,718,140,345) government concessional loan (GCL) agreement [No. 1420303052011111536] for Phase 3 of the Addis Ababa Deep Wells Water Supply Project. The Ethiopian House of Representatives ratified the agreement on December 5, 2011. The borrowing terms of the GCL are as follows: a 2% interest rate, an 8-year grace period, and a 21-year maturity. According to the Government of Ethiopia’s Aid Management Platform (AMP), the loan achieved a 174% disbursement rate, with China Eximbank making 7 loan disbursements (worth ETB 2,988,235,879) between 2013 and 2015: an ETB 548,151,920 disbursement on January 8, 2013, an ETB 366,666,667 disbursement on January 8, 2014, an ETB 366,666,667 disbursement on January 8, 2014, an ETB 314,960,630 disbursement on July 8, 2014, an ETB 540,000,000 disbursement on October 8, 2014, an ETB 606,060,606 disbursement on January 8, 2015, and an ETB 245,729,390 disbursement on July 7, 2015. The purpose of the project was to drill 24 water wells -- including three deep water wells in the Akaki well field areas -- and produce about 10,000 cubic meters of water per a day, thereby benefiting 100,000 people. The project also included 266.3 km of main line installation, 10.5 km distribution line installation, and 25.8 km of collection lines. It also included construction of six water tankers that have the capacity of holding from 1,000 cubic meters of water to 5,000 cubic meters of water. The Akaki well field is located to the southeast of Akaki town about 22 km south of the center of Addis Ababa within the Akaki catchment. CGC Overseas Construction Co. Ltd, (CGCOC) was the EPC contractor responsible for project implementation. Its work was supervised by a local company called Water Works Design and Supervision. Project implementation commenced on November 19, 2012. A project completion ceremony was held on March 8, 2015. There are some indications that the China Eximbank loan for Phase 3 of the Addis Ababa Deep Wells Water Supply Project may have financially underperformed vis-a-vis the original expectations of the lender. According to the Government of Ethiopia’s Aid Management Platform, as of September 2019, ICBC suspended about $67 million worth of loan disbursements 'due to [the] cross-default situation of the country’ (see Project ID#58616). Then, in August 2021, China Eximbank withheld $339 million loan disbursements for 12 projects and halted project implementation due to Government of Ethiopia’s rapidly dwindling foreign exchange reserves and debt sustainability challenges. Demisu Lemma, the Director of Chinese Cooperation at the Ethiopian Ministry of Finance, noted at the time that the Ethiopian Government was in discussions with China Eximbank about a potential debt rescheduling (that would involved a 5-year maturity extension and a 1-year grace period extension). Then, after considerable delay, the G20 Common Framework (CF) creditor committee for Ethiopia convened in September 2021, with the French Government and the Chinese Government serving as co-chairs. The CF debt rescheduling talks were still ongoing in mid-2023.

Additional details

1. This project is also known as the Akaki Underground Water Development Project (Phase 3b), Phase III of the Addis Ababa Deep Wells Water Supply Project, and the Addis Ababa Deep Well Water Supply Project (Phase III). The Chinese project title is 的亚的斯亚贝巴深井供水项目(三期). 2. The system identification number for the project in the Government of Ethiopia’s Aid Management Platform (AMP) is 87143124101632.

Number of official sources

9

Number of total sources

20

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Ethiopia [Government Agency]

Implementing agencies [Type]

CGC Overseas Construction Co., Ltd. (CGCOC) [State-owned Company]

Water Works Design and Supervision [Private Sector]

Loan Details

Maturity

21 years

Interest rate

2.0%

Grace period

8 years

Grant element (OECD Grant-Equiv)

53.8668%

Bilateral loan

Government Concessional Loan

Investment project loan