Project ID: 152

China Eximbank and China Construction Bank provide $90 million export seller’s credit for Phase 1 of the Luanda Railway Rehabilitation Project (Linked to Project ID#67143)

Commitment amount

$ 224950941.18032855

Adjusted commitment amount

$ 224950941.18

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

China Construction Bank Corporation (CCB) [State-owned Commercial Bank]

Recipient

Angola

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Unallocable

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2002-01-01

Actual start

2003-11-13

Actual complete

2009-02-01

Geography

Description

In 2002, China Eximbank and China Construction Bank reportedly issued a $90 million seller’s credit for Phase 1 of the Luanda Railway Rehabilitation Project. The loan was part of a larger $145 million credit line captured via Project ID#67143. The Luanda Railway Rehabilitation Project involved the rehabilitation of a 444 km railway (with 16 stations) from Luanda Province to Malanje Province. Phase 1 of the Luanda Railway Rehabilitation Project covered a 43 km segment of the railway between Baia station and Bungo station along the Luanda Railway Line known as Caminho-de-Ferro de Luanda (CFL). CMEC was the contractor responsible for implementation Construction commenced on November 13, 2003 and was originally expected to be complete by August 2008. The railway was ultimately inaugurated in September 2008. Then, in February 2009, the Bungo-Baia section of the railway came into service.

Additional details

1. The Chinese project title is 中安铁路合作项目 or 安哥拉罗安达铁路修复项目 or 罗安达铁路修复和改造项目第一期工程. 2. Further investigation is needed to determine if the Chinese company or companies that received the export seller’s credit from China Eximbank used the proceeds to issue one or more supplier credits to the Government of Angola. 3. Phase II of the Luanda Railway Rehabilitation Project was financed via China International Fund Ltd. (CIF), a private Hong Kong–based institution, who extended $2.9 billion to assist Angola’s postwar reconstruction effort in 2005. This credit facility is managed by Angola’s Reconstruction Office, Gabinete de Reconstrução Nacional (GRN), which is exclusively accountable to the Angolan presidency. A portion of this credit line was envisioned for Phase II of the Luanda Railway Rehabilitation Project.

Number of official sources

8

Number of total sources

23

Download the dataset

Details

Cofinanced

Yes

Direct receiving agencies [Type]

China Machine-Building International Corporation (CMIC) [State-owned Company]

Implementing agencies [Type]

Government of Angola [Government Agency]

Loan Details

Syndicated loan

Investment project loan

Supplier's credit/Export seller's credit