Skip to content

Overview

China Eximbank provides $260 million preferential buyer’s credit for Phase 1 of Kpong Water Expansion Supply Project (Linked to Record ID#91808)

Commitments (Constant USD, 2023)$334,396,003
Commitment Year2010Country of ActivityGhanaDirect Recipient Country of IncorporationGhanaSectorWater Supply And SanitationFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Sep 20, 2010
Start (actual)
Jun 1, 2011
End (planned)
Jun 1, 2015
End (actual)
May 28, 2015
First repayment
Sep 19, 2015
Last repayment
Sep 15, 2030

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project was to increase the supply of water from Kpong Head Works to Accra and Tema and thereby improve the reliability of potable water delivery to domestic, commercial and industrial customers. It involved construction of a new 353,000 m3 per day intake, expansion of treatment plant to 250,000 m3 per day and construction of new transmission mains through Dodowa, Adenta to Accra Booster Station (in Okponglo near Okponglo Road). Other works involved the provision of dedicated electricity supply, distribution improvement and construction of terminal reservoirs at Madina, Boi and Okpong. The project was implemented in 3 phases. Phase 1 involved the construction of a new intake and water pumping station for bulk water supply from Kpong with capacity of 196,000 cubic meters per day. Phase 2 involved the construction of a new treatment plant of 186,000 cubic meters or 41 million gallons a day. Phase 3 involved the construction of new treated water pumping station as well as a pressure transmission (mains) system from Kpong to Accra through Oyibi to terminate at Okponglo (a suburb of Accra. The project beneficiary areas included Adenta, Madina, Kwabenya, Ashongman, North Legon, East Legon, West Legon, Ashaley Botwe, Haatso, Boi, Asofaa, Dome and surrounding areas. More detailed locational information can be found at: https://www.openstreetmap.org/way/954006574 and https://www.openstreetmap.org/way/954006571 and https://www.openstreetmap.org/way/954006574 and https://www.openstreetmap.org/way/787277207 and https://www.openstreetmap.org/relation/12803764 and https://www.openstreetmap.org/relation/12758446 and https://www.openstreetmap.org/node/738942517 and https://www.openstreetmap.org/node/2148020762 and https://www.openstreetmap.org/node/4509337287 and https://www.openstreetmap.org/node/2152138370

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Ghana Ministry of Finance

State-owned companies

  • Ghana Water Company Ltd.

Implementing agencies

State-owned companies

  • China Gezhouba Water and Power Group, ltd.
  • Ghana Water Company Ltd.

Loan desecription

China Eximbank provides $260 million preferential buyer’s credit for Phase 1 of Kpong Water Expansion Supply Project

Grace period5 yearsGrant element53.1012%Interest rate (t₀)2%Interest typeFixed Interest RateMaturity20 years

Narrative

Full Description

Project narrative

On September 20, 2010, China Eximbank and the Government of Ghana’s Ministry of Finance and Economic Planning signed a $260,000,000 preferential buyer's credit (PBC) agreement for Phase 1 of the Kpong Water Expansion Supply Project (captured via Record ID#2004). The PBC carries the following borrowing terms: a 21.25 year maturity, a 5 year grace period, a 2% interest rate, a 0.75% commitment fee, and a 1% management fee. The total project cost is $273 million. China Eximbank covered 95% of the total project cost and the Government of Ghana covered the remaining 5% ($13 million). The Government of Ghana used proceeds from the PBC to on-lend to Ghana Water Company Limited (GWCL), a Ghanaian state-owned company, a Ghanaian state-owned enterprise. To this end, the Government of Ghana signed a $276,250,000 subsidiary loan agreement with the GWCL on August 25, 2015. The subsidiary loan carries a 15 year maturity and a 2% interest rate. The (principal) amount outstanding under the China Eixmbnak loan (PBC) was GHS 991,940,000 ($177,132,142) as of December 31, 2020 and GHS 933,500,000 ($179,519,230) as of December 31, 2021. The purpose of the Kpong Water Expansion Supply Project was to increase the supply of water from Kpong Head Works to Accra and Tema and thereby improve the reliability of potable water delivery to domestic, commercial and industrial customers. It involved construction of a new 353,000 m3 per day intake, expansion of treatment plant to 250,000 m3 per day and construction of new transmission mains through Dodowa, Adenta to Accra Booster Station. Other works involved the provision of dedicated electricity supply, distribution improvement and construction of terminal reservoirs at Madina, Boi and Okpong. The project was implemented in 3 phases. Phase 1 involved the construction of a new intake and water pumping station for bulk water supply from Kpong with capacity of 196,000 cubic meters per day. Phase 2 involved the construction of a new treatment plant of 186,000 cubic meters or 41 million gallons a day. Phase 3 involved the construction of new treated water pumping station as well as a pressure transmission (mains) system from Kpong to Accra through Oyibi to terminate at Okponglo (a suburb of Accra). The project beneficiary areas included Adenta, Madina, Kwabenya, Ashongman, North Legon, East Legon, West Legon, Ashaley Botwe, Haatso, Boi, Asofaa, Dome and surrounding areas. China Gezhouba Water and Power Group Company Limited was the contractor responsible for implementation. Its work was overseen by Ghana Water Company Limited (GWCL). Construction began on June 1, 2011 and official project completion ceremony took place on December 23, 2014. However, the project was not fully complete until May 28, 2015. The originally scheduled contractual completion date was June 2015. In 2019, Ghana Water Company Limited (GWCL) was reportedly negotiating a $373,000,000 loan agreement with China Eximbank to fund the second phase of this project (captured via Record ID#91808). The Government of Ghana's Development Co-operation Management Information System (Gh-DCMIS) identifies this pipeline project as having an expected loan signing date of August 25, 2022, an expected project commencement date of August 10, 2022, and an expected project completion date of August 30, 2023. There are some indications that the China Eximbank loan for Phase 1 of the Kpong Water Expansion Supply Project may have financially underperformed vis-a-vis the original expectations of the lender. According to the World Bank’s International Development Statistics, the Government of Ghana had accumulated principal and interest arrears to one or more official sector Chinese creditors worth $908,337,346.70) in 2020 ($763,228,526.60 in principal arrears and $145,108,820.10 in interest arrears). Then, on December 19, 2022, the Government of Ghana announced a sovereign default, suspending debt service on its Eurobonds, its commercial loans, and most of its bilateral loans.

Staff comments

1. The Chinese project title is 凯蓬供水扩建工程项目 or 加纳凯蓬供水项目. 2. In the database of Chinese loan commitments that SAIS-CARI released in July 2020, it records the maturity length of this loan as 15 years. However, AidData records a maturity length of 20 years since multiple official sources cite this figure and Ghana’s Ministry of Finance and Economic Planning identified the loan agreement date as September 20, 2010 and final maturity date as January 21, 2031. 3. The (principal) amounts outstanding are drawn from the Ghanaian Ministry of Finance’s Annual Public Debt Reports. These amounts are reported in GHS by the Ministry of Finance. AidData has estimated the USD amounts by applying the average GHS-to-USD exchange rate in 2020 (5.6-to-1) and the average GHS-to-USD exchange rate in 2021 (5.2-to-1). 4. The Loan/Grant Code and Project Identification number for Phase 2 of the Kpong Water Expansion Supply Project in the Gh-DCMIS) are CH-GH-2021 and GHA/000927. 2010021 is the ID assigned to the loan in the Ghanaian Auditor General Reports