Project ID: 22643

Chinese Government provides RMB 40 million grant for Phase I of Agricultural Technology Demonstration Center Project (Linked to #85314, Umbrella #47332)

Commitment amount

$ 8774456.765736308

Adjusted commitment amount

$ 8774456.77

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Sudan

Sector

Agriculture, forestry, fishing (Code: 310)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2008-01-24

Actual start

2009-04-11

Actual complete

2011-06-16

Geography

Description

On 25 January 2008, Chinese Ambassador Li Chengwen and Sudan's Agriculture and Forests Minister Alaghbash signed a grant agreement for Phase 1 of the Agricultural Technology Demonstration Center Project in Al Faw (الفاو) district within Al Qadarif State. Phase I of the project was reportedly financed with an RMB 40 million grant from the Chinese Government. This project was partially financed by a Chinese Government grant signed in June 2008 (see Umbrella Project #47332). On 26 October, 2008, Sudanese Government officials signed a construction contract with China Shandong International Economic and Technical Cooperation Corporation. China Oil & Gas Eastern Survey and Design Research Institute (a subsidiary of CNPC) also aided in the design of the center, while Guangdong Overseas Construction Supervision Co., Ltd. aided in supervision of the project. The purpose of Phase I was to build the physical structures associated with the center. The center sits on 60 hectares and is used for improving crop yields, production demonstrations, and training of personnel. A groundbreaking ceremony took place on 11 April 2009 and the project was completed in March 2011. Then, on 16 June 2011, Chinese and Sudanese officials signed a certificate officially handing over the Agricultural Technology Demonstration Center to the Government of Sudan. Following construction, the center moved into Phase II, technical cooperation and operation, which will be followed by Phase III, sustainable development. Phase II is being funded with a separate RMB 14.6 million grant from China’s Ministry of Commerce (see Project #85314).

Additional details

The Chinese project title is 援苏丹农业技术示范中心项目 or 苏丹农业技术示范中心项目. Phase I is captured in Project #22643 and Phase II is captured in Project #85314.

Number of official sources

15

Number of total sources

22

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Sudan [Government Agency]

Implementing agencies [Type]

China National Petroleum Corporation (CNPC) [State-owned Company]

Guangdong Overseas Construction Supervision Co., Ltd. [Private Sector]

China Shandong International Economic and Technical Cooperation Corporation (SIETC) [State-owned Company]