Chinese Government finances Government Office Building Construction Project

Commitment Year2006Country of ActivityMauritaniaDirect Recipient Country of IncorporationMauritaniaSectorGovernment And Civil SocietyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Mar 22, 2006
Start (actual)
Dec 30, 2008
End (actual)
Aug 2, 2010

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to finance the government office building construction project. More detailed location information can be found at https://www.openstreetmap.org/relation/3395130

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • Unspecified Chinese Government Institution

Receiving agencies

Government Agencies

  • Government of Mauritania

Implementing agencies

State-owned companies

  • China Zhongyuan International Engineering Co., Ltd.

Loan desecription

Chinese Government finances Government Office Building Construction Project

Narrative

Full Description

Project narrative

In 2006, the Chinese Government agreed to fund the Government Office Building Construction Project in Mauritania. The monetary value of this financial commitment is unknown. This project involved the construction of three government office buildings in the capital city of Nouakchott. The buildings that were constructed were earmarked for use by the Prime Minister's Office, the Ministry of Foreign Affairs and Cooperation, and other departmental functions. The buildings were 3,000, 4,000 and 5,000 square meters, respectively. China Zhongyuan International Engineering Co., Ltd. — a subsidiary of Sinomach — was the contractor responsible for implementation. It signed a construction contract on August 6, 2008. Construction began on December 30, 2008, and the project was completed on August 2, 2010. An official handover ceremony took place on September 23, 2010.

Staff comments

The Chinese project title is 政府办公楼项目 or 毛里塔尼亚政府办公楼项目 or 援毛里塔尼亚政府办公楼项目.