Skip to content

Overview

ICBC provides $69.7 million buyer’s credit for 35MW Broadlands Hydropower Project

Commitments (Constant USD, 2023)$72,067,799
Commitment Year2013Country of ActivitySri LankaDirect Recipient Country of IncorporationSri LankaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Mar 12, 2013
Start (planned)
Jan 15, 2013
Start (actual)
Jul 17, 2013
First repayment
Mar 11, 2016
Last repayment
Mar 12, 2028

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved the construction of 35 MW run-of-the-river hydroelectric complex over the Kelani River in Kitulgala. More specifically, it involved the construction of a 24m high & 144m long main dam, a 19m high & 48m long diversion dam, a 2.7m diameter & 850m long diversion tunnel, a 5.4m diameter & 3 km long main tunnel, a 35MW surface power station (2 units of 17.5MW), a switch yard, and a 4 km long transmission line. The complex has an installed capacity of 35 MW and is expected to generate 126 GWh of electrical energy annually. Its exact locational coordinates are 06°58′44″N 80°27′16″E. More detailed locational information can be found at https://www.openstreetmap.org/node/5619440318

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Commercial Banks

  • Industrial and Commercial Bank of China (ICBC)

Cofinancing agencies

Private Sector

  • Hatton National Bank PLC (HNB)

Receiving agencies

State-owned companies

  • Ceylon Electricity Board

Implementing agencies

State-owned companies

  • Ceylon Electricity Board
  • China National Electric Engineering Co., Ltd. (CNEEC)

Accountable agencies

Government Agencies

  • Government of Sri Lanka

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Guarantors

Government Agencies

  • Government of Sri Lanka

Insurance providers

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Loan desecription

ICBC provides $69.7 million buyer’s credit for 35MW Broadlands Hydropower Project

Grace period3 yearsGrant element34.4971%Interest rate (t₀)3.6459%Interest typeVariable Interest RateLoan tenor6-month rateMaturity15.012 years

Narrative

Full Description

Project narrative

On March 12, 2013, ICBC and the Ceylon Electricity Board signed a $69.7 million buyer’s credit (loan) agreement for the 35MW Broadlands Hydropower Project. This loan carries the following borrowing terms: a grace period of 3 years, a maturity of 15 years, and an interest rate of 6-month LIBOR plus a 3.2% margin. The loan’s final maturity date is March 12, 2028. The Government of Sri Lanka issued a sovereign guarantee in support of the loan. Sinosure provided buyer’s credit insurance. The proceeds of the $69.7 million ICBC loan were to be used by the borrower to finance 85% of the total cost of an $82 million commercial contract with China National Electricity Equipment Corporation, which was signed on October 20, 2010. Hatton National Bank of Sri Lanka financed the remaining 15% of the project cost. The principal amount outstanding under the ICBC loan was $6.05 million as of December 31, 2015, $17.18 million as of December 31, 2016, $28 million as of December 31, 2017, $24.98 million as of December 31, 2018, $23.13 million as of December 31, 2019, and $30.95 million as of December 31, 2020. The project involved the construction of 35 MW run-of-the-river hydroelectric complex over the Kelani River in Kitulgala. Its exact locational coordinates are 06°58′44″N 80°27′16″E. More specifically, the project involved the construction of a 24 meter high & 144 meter long main dam, a 19 meter high & 48 meter long diversion dam, a 2.7 meter diameter & 850 meter long diversion tunnel, a 5.4 meter diameter & 3 km long main tunnel, a 35MW surface power station (2 units of 17.5MW), a switch yard, and a 4 km long transmission line. The complex has an installed capacity of 35 MW and is expected to generate 126 GWh of electrical energy annually. The contractor responsible for implementation was China National Electric Equipment Corporation. Its work was supervised by Ceylon Electricity Board, the largest electricity company in Sri Lanka. Construction was originally expected to commence on January 15, 2013; however, it ultimately began on July 17, 2013. River closure took place on November 20, 2016. On June 6, 2019, a breakthrough ceremony of the main headrace tunnel took place. As of August 2020, the project had achieved a 74.79% completion rate. Then, in November 2021, an inaugural ceremony was held for the release of water to the main tunnel of the Broadlands Hydropower Project.

Staff comments

1. The Chinese project title is 斯里兰卡布罗德兰水电站主. 2. AidData has estimated the all-in interest rate (3.648%) by adding 3.2% to average 6-month rate LIBOR (0.448%) in March 2013. 3. Some sources identify the loan commitment date as January 16, 2013. Ceylon Electricity Board's 2021 annual report states the loan grant date to be June 6, 2013. This discrepancy warrants further investigation. 4. Ceylon Electricity Board is a government-owned and controlled utility of Sri Lanka that takes care of the general energy facilities of the island.