Project ID: 34154

Chinese Government provides RMB 60 million grant for Kiffa Health Center Project (Linked to Project ID#18750 and #56843)

Commitment amount

$ 11414980.559306381

Adjusted commitment amount

$ 11414980.56

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Mauritania

Sector

Health (Code: 120)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2011-04-12

Actual start

2013-12-24

Actual complete

2016-04-15

Geography

Description

According to the Government of Mauritania’s Development Assistance Database (DAD), the Chinese Government and the Government of Mauritania signed an Economic and Technical Cooperation Agreement (ETCA) on December 29, 2010, which committed an RMB 60 million interest-free loan for the Kiffa Health Center Project. Then, on April 12, 2011, the Chinese Government and the Government of Mauritania signed letters of exchange, which committed an additional RMB 60 million grant for the same project. Finally, on January 8, 2013, the Chinese Government provided an additional RMB 100 million grant for the Kiffa Health Center Project as well as the provision of school materials. The RMB 60 million interest-free loan is captured in Project ID#18750. The RMB 60 million grant is captured in Project ID#34154. The RMB 100 million grant is captured in Project ID#56843. The Kiffa Health Center Project involved the construction of a 150-bed medical facility with surgical, pediatric, obstetrics and gynecology, cardiovascular, and other departments. YCIH Installation Co. Ltd. (云南建投安装股份有限公司) was the contractor responsible for implementation. The project commenced on December 24, 2013, and ended on April 15, 2016. The official handover ceremony occurred on June 22, 2016. Upon completion, the Kiffa Health Center reportedly accommodated 200 staff members, including 8 Chinese medical staff.

Additional details

The Chinese project title is 基法医疗中 or 中国援毛基法医疗中心 or 基法卫生中心项目 or 援毛里塔尼亚基法卫生中心. The French project title is Centre Hôpitalier de Kiffa. The Arabic project title is مستشفى كيفة. The RMB 60 million interest-free loan that supported the Kiffa Health Center Project does not appear to be included in the database of Chinese loan commitments that SAIS-CARI released in July 2020.

Number of official sources

10

Number of total sources

14

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Mauritania [Government Agency]

Implementing agencies [Type]

Yunnan Construction Engineering Group Corporation (YNJG) [State-owned Company]