Project ID: 35982

China Eximbank provides $312.4 million buyer's credit loan for 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project (Linked to Project ID#93434 and #96295)

Commitment amount

$ 352489952.63962567

Adjusted commitment amount

$ 352489952.64

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Ecuador

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government debt

Financial distress

Yes

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2013-04-10

Actual start

2012-03-01

Actual complete

2021-04-09

Geography

Description

On April 10, 2013, China Eximbank and the Government of Ecuador signed a $312,480,966.99 buyer's credit loan (BCL) agreement (Contract No. 1410302052013210568) for the 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project. The BCL carried the following borrowing terms: an annual interest rate of 6 month LIBOR plus a 4.2% margin, a grace period of 4 years, and a maturity of 15 years. It is backed by a credit insurance policy from Sinosure. As of December 2018, the loan had achieved an 31.9% disbursement rate ($99,967,764.14 out of $312,480,967). The borrower made principal repayments worth $15,624,048.35 on September 21, 2018, $15,624,048.35 on March 21, 2019, $15,624,048.35 on September 21, 2019, $15,624,048.35 on March 21, 2020, and $19,229,597.97 on March 21, 2022. It did not make any principal repayments on the originally scheduled repayment dates of September 21, 2020, March 21, 2021, September 21, 2021, and September 21, 2022. The loan’s (principal) amount outstanding was $298,856,918.64 September 21, 2018, $281,232,870.29 as of March 21, 2019, $265,608,821.94 as of September 21, 2019, $249,984,773.59 as of March 21, 2020, $249,984,773.59 as of September 21, 2020, $249,984,773.59 as of March 21, 2021, $249,984,773.59 as of September 21, 2021, $249,984,773.59 as of December 31, 2021, $230,755,175.62 as of March 21, 2022, $230,755,175.62 as of September 21, 2022, and $230,755,175.62 as of November 30, 2022. The purpose of the project was to construct the 275MW Minas-San Francisco Hydroelectric Power Plant in the southwest province of Azuay and the cantons of El Oro, Pucará, Zaruma and Pasaje. Upon completion, the power plant was expected to have a maximum annual power generation capacity of 1.291 billion kWh and reduce carbon emissions by 690,000 tons each year. Minas San Francisco is made up of a 54-m-high rolled concrete gravity-type dam that generates a regulation and control reservoir, an intake work located on the right bank of the Jubones River that connects with a 13.9 km driving tunnel. The pressure pipe is developed in two sections that comprise a total drop of 474 meter. The underground powerhouse houses three Pelton-type turbines of 90 MW each. Harbin Electric International Company Limited was the general contractor responsible for implementation. Its work was overseen by Corporación Eléctrica del Ecuador (CELEC) and Ministerio de Electricidad y Energía Renovable (MEER). Construction began in March 2012. The excavation of a diversion tunnel was completed in August 2013. The diversion of the Jubones River took place in February 2014. Then, in January 2015, the excavation of the entrance window to the head tunnel was complete. The completion of the powerhouse excavation took place in October 2015. Then, in December 2016, the construction and assembly of the transmission line was completed. The power plant’s three generator rotors were lowered into place between January 2017 and May 2017. The filling of the reservoir occurred in December 2017. Then, in May 2018, the first rotation of the first turbine-generator took place. As of August 2018, the project had achieved a 99.7% completion rate. All three power generation units were connected to the grid on October 24, 2018. The first power generation unit was officially inaugurated on January 15, 2019. The project’s official handover ceremony took place on April 9, 2021. To date, the power plant has reportedly generated over 140 million kWh power, created more than 2,000 jobs, and delivered electricity on a daily basis to nearly 1.2 million people and 2,000 manufacturing companies. However, the project suffered multiple setbacks due to administrative and technical discrepancies with contractors and inspectors, as well as the COVID-19 pandemic. The China Eximbank loan (BCL) that supported this project also underperformed. It was rescheduled twice — once in September 2020 (as captured via Project ID#93434) and again in September 2022 (as captured via Project ID#96295).

Additional details

1. The Chinese project title is 厄瓜多尔米纳斯圣弗朗西斯科水电站项目. The Spanish project title is La Central Hidroeléctrica Minas San Francisco de 270 MW. 2. The all-in interest was estimated by adding 4.2% to the average 6 month Libor rate in April 2013 (0.154%). 3. The Ministry of Finance SAP code for this project is 202021003. 4. The September 2022 loan rescheduling agreement can be accessed in its entirety via https://www.dropbox.com/s/7y7w2q91up5ukcn/13%20September%202022%20Amendment%20Agreement%20related%20to%20BCL%20for%20Minas%20San%20Francisco%20Project.pdf?dl=0. The revised loan amortization table (repayment schedule) can be accessed on pg. 6. 5. The Ecuadorian Ministry of Finance loan identification number is 23171000

Number of official sources

14

Number of total sources

35

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Ecuador [Government Agency]

Implementing agencies [Type]

Corporacion Electrica del Ecuador (CELEC) [State-owned Company]

Government of the Republic of Ecuador [Government Agency]

Ministerio de Electricidad y Energía Renovable (MEER) (Ecuador) [Government Agency]

Harbin Electric International Co., Ltd. (HEI) [State-owned Company]

Insurance provider [Type]

China Export & Credit Insurance Corporation (Sinosure) [State-owned Company]

Loan Details

Maturity

15 years

Interest rate

4.354%

Grace period

4 years

Grant element (OECD Grant-Equiv)

10.9213%

Bilateral loan

Export buyer's credit

Investment project loan