Skip to content

Overview

China Eximbank provides $312.4 million buyer's credit loan for 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project (Linked to Record ID#93434 and #96295)

Commitments (Constant USD, 2023)$323,096,349
Commitment Year2013Country of ActivityEcuadorDirect Recipient Country of IncorporationEcuadorSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Apr 10, 2013
Start (actual)
Mar 1, 2012
End (actual)
Apr 9, 2021
First repayment
Oct 30, 2018
Last repayment
Apr 6, 2028

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

Minas-San Francisco hydroelectric plant (Central Hidroeléctrica Minas San Francisco) is located on the Jubones River. More detailed locational information can be found at https://www.openstreetmap.org/way/928750864#map=16/-3.3099/-79.5989

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Ecuador

Implementing agencies

Government Agencies

  • Government of Ecuador
  • Ministerio de Electricidad y Energía Renovable (MEER) (Ecuador)

State-owned companies

  • Corporacion Electrica del Ecuador (CELEC)
  • Harbin Electric International Co., Ltd. (HEI)

Insurance providers

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Loan desecription

China Eximbank provides $312.4 million buyer's credit loan for 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project

Grace period5.56 yearsGrant element32.4453%Interest rate (t₀)4.5734%Interest typeVariable Interest RateLoan tenor6-month rateMaturity15 years

Narrative

Full Description

Project narrative

On November 9, 2012, China Eximbank and the Government of the Republic of Ecuador signed a term sheet related to the financing of the 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project. Then, on April 10, 2013, China Eximbank and the Government of the Republic of Ecuador signed a $312,480,966.99 buyer's credit loan (BCL) agreement (Contract No. 1410302052013210568) for the 275MW Minas-San Francisco Hydroelectric Power Plant Construction Project. The BCL carried the following borrowing terms: an annual interest rate of 6 month LIBOR plus a 4.2% margin, a grace period of 5.56 years, a maturity of 15 years, a 0.6% management fee ($1.874,885.80), a 0.6% commitment fee, and a 1.5% default (penalty) interest rate. It is backed by a credit insurance policy from Sinosure. The borrower was responsible for making 22 equal, semiannual principal payments (worth $14,203,680). The borrower was expected to use the proceeds of the loan to finance 66% of the cost of a commercial contract (payable in a $327,480,967 tranche and an RMB 944,239,050.56 tranche) between Corporación Eléctrica del Ecuador (CELEC E.P.) and Harbin Electric International Company Limited, which was signed on December 30, 2011. As of December 2018, the loan had achieved an 31.9% disbursement rate ($99,967,764.14 out of $312,480,967). The borrower made principal repayments worth $15,624,048.35 on September 21, 2018, $15,624,048.35 on March 21, 2019, $15,624,048.35 on September 21, 2019, $15,624,048.35 on March 21, 2020, and $19,229,597.97 on March 21, 2022. It did not make any principal repayments on the originally scheduled repayment dates of September 21, 2020, March 21, 2021, September 21, 2021, and September 21, 2022. The loan’s (principal) amount outstanding was $298,856,918.64 September 21, 2018, $281,232,870.29 as of March 21, 2019, $265,608,821.94 as of September 21, 2019, $249,984,773.59 as of March 21, 2020, $249,984,773.59 as of September 21, 2020, $249,984,773.59 as of March 21, 2021, $249,984,773.59 as of September 21, 2021, $249,984,773.59 as of December 31, 2021, $230,755,175.62 as of March 21, 2022, $230,755,175.62 as of September 21, 2022, and $230,755,175.62 as of November 30, 2022. The purpose of the project was to construct the 275MW Minas-San Francisco Hydroelectric Power Plant in the southwest province of Azuay and the cantons of El Oro, Pucará, Zaruma and Pasaje. Upon completion, the power plant was expected to have a maximum annual power generation capacity of 1.291 billion kWh and reduce carbon emissions by 690,000 tons each year. Minas San Francisco is made up of a 54-m-high rolled concrete gravity-type dam that generates a regulation and control reservoir, an intake work located on the right bank of the Jubones River that connects with a 13.9 km driving tunnel. The pressure pipe is developed in two sections that comprise a total drop of 474 meter. The underground powerhouse houses three Pelton-type turbines of 90 MW each. Harbin Electric International Company Limited was the general contractor responsible for implementation. Its work was overseen by Corporación Eléctrica del Ecuador (CELEC) and Ministerio de Electricidad y Energía Renovable (MEER). Construction began in March 2012. The excavation of a diversion tunnel was completed in August 2013. The diversion of the Jubones River took place in February 2014. Then, in January 2015, the excavation of the entrance window to the head tunnel was complete. The completion of the powerhouse excavation took place in October 2015. Then, in December 2016, the construction and assembly of the transmission line was completed. The power plant’s three generator rotors were lowered into place between January 2017 and May 2017. The filling of the reservoir occurred in December 2017. Then, in May 2018, the first rotation of the first turbine-generator took place. As of August 2018, the project had achieved a 99.7% completion rate. All three power generation units were connected to the grid on October 24, 2018. The first power generation unit was officially inaugurated on January 15, 2019. The project’s official handover ceremony took place on April 9, 2021. To date, the power plant has reportedly generated over 140 million kWh power, created more than 2,000 jobs, and delivered electricity on a daily basis to nearly 1.2 million people and 2,000 manufacturing companies. However, the project suffered multiple setbacks due to administrative and technical discrepancies with contractors and inspectors, as well as the COVID-19 pandemic. The China Eximbank loan (BCL) that supported this project also underperformed. It was rescheduled twice — once in September 2020 (as captured via Record ID#93434) and again in September 2022 (as captured via Record ID#96295).

Staff comments

1. The Chinese project title is 厄瓜多尔米纳斯圣弗朗西斯科水电站项目. The Spanish project title is La Central Hidroeléctrica Minas San Francisco de 270 MW. 2. The all-in interest was estimated by adding 4.2% to the average 6 month Libor rate in April 2013 (0.154%). 3. The Ministry of Finance SAP code for this project is 202021003. 4. The loan agreement can be accessed in its entirety via https://www.dropbox.com/scl/fi/na46pgqfr3m5ksbvwy368/Ecuador-2013-China-Eximbank-Buyer-s-Credit-Loan-for-the-275MW-Minas-San-Francisco-Hydroelectric-Power-Plant-Construction-Project.pdf?rlkey=cnfituxb0fh99fdjczom7uadw&dl=0 5. The September 2022 loan rescheduling agreement can be accessed in its entirety via https://www.dropbox.com/s/7y7w2q91up5ukcn/13%20September%202022%20Amendment%20Agreement%20related%20to%20BCL%20for%20Minas%20San%20Francisco%20Project.pdf?dl=0. The revised loan amortization table (repayment schedule) can be accessed on pg. 6. 6. The Ecuadorian Ministry of Finance loan identification number is 23171000