Project ID: 37473

Chinese Government provides $26.5 million grant for Government Administrative Office Complex (AOC) Construction Project

Commitment amount

$ 29347712.641945463

Adjusted commitment amount

$ 29347712.64

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Rwanda

Sector

Government and civil society (Code: 150)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2014-01-01

Actual start

2016-07-15

Planned complete

2019-03-31

Actual complete

2019-02-28

Geography

Description

Set implementing_agencies field to Top International Engineering Corporation, State-Owned Company; Shandong Construction Supervision Consulting Co., Ltd., State-Owned Company; Co., Ltd., State-Owned Company. On August 11, 2014, China's Ambassador to Rwanda H.E. Mr. SHEN Yongxiang announced that his government would provide a grant worth $26,508,751.74 for the Government Administrative Office Complex (AOC) Construction Project. The purpose of this project was to construct a Government Administrative Office Complex (AOC) in the capital city of Kigali (exact locational coordinates: -1.9562166028304055, 30.084386849071564. The project involved the construction of a complex that would cover 20,000 square meters with a total floor space of about 16,377 square meters and an eight-story main office building. The complex houses the Prime Minister’s Office, Ministry of Infrastructure, Ministry of Justice and the Rwanda Law Reform Commission. It can accommodate 1,110 people. CITIC Architectural Design and Research Institute Co., Ltd. was the contractor responsible for project design. Top International Engineering Corporation (also known as Huashan International Engineering Company) was the contractor responsible for implementation. Shandong Construction Supervision Consulting Co., Ltd. was the contractor responsible for project supervision. A foundation-laying ceremony took place on March 23, 2016. However, construction did not begin until July 15, 2016. Then, on August 29, 2018, Rwanda’s Prime Minister conducted an on-site project inspection. The project was completed on February 28, 2019. A formal handover and inauguration ceremony was held on April 22, 2019. The new complex is expected to help the Rwandan Government cut office rent expenditures, Claver Gatete, Rwanda's Minister of Infrastructure, told journalists in 2019 that the Rwandan Government had spent more than $4.4 million to rent offices for about 30 public institutions over the prior 10-year period.

Additional details

1. This project is also known as the Administrative Office Complex Construction Project. The Chinese project title is 卢旺达综合办公楼项 or 援卢旺达政府综合办公楼项目.

Number of official sources

22

Number of total sources

34

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Rwanda [Government Agency]

Implementing agencies [Type]

Top International Engineering Corporation [State-owned Company]

Shandong Construction Supervision Consulting Co., Ltd. [State-owned Company]

CITIC Architectural Design and Research Institute [State-owned Company]