China Eximbank provides $276.25 preferential buyer's credit for Rajshahi Surface Water Treatment Plant Project

Commitments (Constant USD, 2023)$276,250,000
Commitment Year2023Country of ActivityBangladeshDirect Recipient Country of IncorporationBangladeshSectorWater Supply And SanitationFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
May 10, 2023
Start (actual)
Jul 1, 2023
End (planned)
Jul 1, 2026
First repayment (originally scheduled)
May 8, 2028
Last repayment (originally scheduled)
May 5, 2043

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to construct a surface water treatment plant in Rajshahi to increase water supply as well as population coverage and to make a sustainable water supply system through 100% water supply from surface water sources. It will involve the installation of an intake, a conventional treatment plant, treated water transmission mains, and a booster pump station. The project will also seek to establish a primary and secondary distribution network in Godagari. More detailed locational information about the Rajshahi Water Treatment Plant can be found at: https://www.openstreetmap.org/way/553940769

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Bangladesh

Implementing agencies

State-owned companies

  • Hunan Construction Engineering Group Co., Ltd.

Loan desecription

China Eximbank provides $276.25 preferential buyer's credit for Rajshahi Surface Water Treatment Plant Project

Grace period5 yearsGrant element53.1012%Interest rate (t₀)2%Interest typeFixed Interest RateMaturity20 years

Narrative

Full Description

Project narrative

In 2014, China Eximbank agreed in principle to provide a $500 million loan to the Government of Bangladesh to build the Rajshahi Surface Water Treatment Plant. The project aims to provide 200 million liters of surface water every day. Besides, the plant will supply water to all of the areas of the region by 2035. In January 2015, China Eximbank requested that Bangladesh expedite the commercial contract signing process of the project could commence. The Executive Committee for the National Economic Council (ECNEC) finally approved the project in October 2018. Then, in 2020, a report indicated that the Bangladeshi authorities submitted a request for a $276.25 million loan to the Chinese authorities. The Chinese embassy replied that the authorities were evaluating the loan. Several years later, on May 10, 2023, the Government of Bangladesh and China Eximbank signed a $276.25 million preferential buyer’s credit agreement. The loan carries a 2% interest rate, a 20-year maturity, a 5-year grace period, a 0.25% commitment fee, and a 0.25% management fee. The borrower is expected to use the proceeds of the loan to finance 85% of the cost of a $325 million commercial (EPC) contract between Hunan Construction Engineering Group Ltd. (HNCEG) and the Rajshahi Water Supply & Sewerage Authority (Rajshahi WASA), which was signed on March 21, 2021. As of the June 30, 2023, the China Eximbank loan (PBC) had achieved a 20% disbursement rate ($55.25 million out of $276.25 million). The objective of the project is to construct a surface water treatment plant in Rajshahi to increase water supply as well as population coverage and to make a sustainable water supply system through 100% water supply from surface water sources. It will involve the installation of an intake, a conventional treatment plant, treated water transmission mains, and a booster pump station. The project will also seek to establish a primary and secondary distribution network in Godagari. Upon completion, the plant is expected to supply two hundred million liters of clean water on daily basis to Rajshahi city and its surrounding areas, thereby solving domestic and industrial water problems and improving people’s livelihoods. HNCEG is the EPC contractor responsible for implementation. The project officially commenced in July 2023. Its originally expected project implementation period was 48 months.

Staff comments

1. The Chinese name for the project is 拉杰沙希地表水处理厂项目. 2. The Government of Bangladesh loan identification number is B1120230510A.