Skip to content

Overview

China Eximbank provides $293.2 million loan for 630MW Pacitan Power Plant Construction Project

Commitments (Constant USD, 2023)$406,797,729
Commitment Year2009Country of ActivityIndonesiaDirect Recipient Country of IncorporationIndonesiaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jul 17, 2009
Start (actual)
Apr 1, 2008
End (actual)
Aug 21, 2013
First repayment (originally scheduled)
Jul 16, 2012
Last repayment (originally scheduled)
Jul 13, 2024

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project was to install a 630-megawatt (MW) coal-fired power plant — with two 315MW generators (Unit 1 and Unit 2) — in Sudimoro District, Pacitan Regency, and East Java Province (locational coordinates: -8.2578176, 111.373558). More detailed locational information can be found at https://www.openstreetmap.org/way/270788980#map=16/-8.2601/111.3741

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

State-owned companies

  • PT Perusahaan Listrik Negara (Persero) (PLN)

Implementing agencies

State-owned companies

  • Hubei Electric Power Construction No.2 Engineering Company

Loan desecription

China Eximbank provides $293.2 million loan for 630MW Pacitan Power Plant Construction Project

Grace period3 yearsGrant element33.7774%Interest rate (t₀)3.77125%Interest typeVariable Interest RateLoan tenor6-month rateMaturity15 years

Narrative

Full Description

Project narrative

On July 17, 2009, China Eximbank and Perusahaan Listrik Negara (PLN) — an Indonesian state electricity distribution company — signed a $293,226,064 loan agreement for the 630MW Pacitan Power Plant Construction Project. The loan carried the following terms: a 15-year maturity, a 3 year grace period, and an interest rate of 6-month LIBOR (0.981% in July 2009) + a 2.8% margin. The proceeds of the loan were to be used by the borrower to partially finance the $345 million cost of an EPC contract between PLN and a consortium consisting of Southwest Electric Power Design Institute, Hongyuan Co, Hubei Second Electric Power Construction Co and Gansu First Construction, which was signed on October 23, 2007. The purpose of the project was to install a 630-megawatt (MW) coal-fired power plant — with two 315MW generators (Unit 1 and Unit 2) — in Sudimoro District, Pacitan Regency, and East Java Province (locational coordinates: -8.2578176, 111.373558). Construction began in April 2008. Unit 1 was connected to the national grid on May 22, 2012 and it began commercial operations on June 24, 2013. Unit 2 was connected to the national grid on September 6, 2012, and began commercial operations on August 21, 2013. There have been extensive negative environmental impacts linked to the project, from loss of biodiversity and livelihoods to lack of compensation.

Staff comments

1. This project is also known as the 2x315MW Pacitan Power Plant Construction Project and the 2x315MW PLTU 1 Jatim Coal-fired Pacitan Power Station Project. The Chinese project title is 巴齐丹项目 or 印尼巴基旦电站项目 or 印尼巴齐丹2×315MW燃煤电厂项目. 2. This project was part of the Government of Indonesia’s ‘fast-track program’.