China Eximbank provides $198.7 million preferential buyer's credit for Phase 1 of Solo-Kertosono Toll Road Project

Commitments (Constant USD, 2023)$207,955,189
Commitment Year2015Country of ActivityIndonesiaDirect Recipient Country of IncorporationIndonesiaSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Dec 29, 2015
Start (actual)
Apr 1, 2015
End (actual)
Dec 20, 2018
First repayment
Dec 27, 2020
Last repayment
Dec 25, 2030

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of Phase 1 was to construct the two-way four-lane Saradan-Kertosono section of the Solo-Kertosono Toll Road (AH2), which is 38.39 km in length. This project, which is located on the island of Java, also involved the construction of 23 bridges in 15 locations with a total length of 659 meters; construction of 1.32 km of access roads; construction of 9 overpasses and 29 underpasses; construction of 1 interchange; and construction of 1 pedestrian bridge. More detailed locational information can be found at https://www.openstreetmap.org/relation/12430973#map=12/-7.5867/111.6791

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Indonesia

Implementing agencies

State-owned companies

  • China Road & Bridge Corporation (CRBC)
  • PT Wijaya Karya Tbk (Wika)
  • PT. PP. (Persero) Tbk

Loan desecription

China Eximbank provides $198.7 million preferential buyer's credit for Phase 1 of Solo-Kertosono Toll Road Project

Grace period5 yearsGrant element41.4363%Interest rate (t₀)3%Interest typeFixed Interest RateMaturity15 years

Narrative

Full Description

Project narrative

On December 29, 2015, China Eximbank and the Government of Indonesia signed a $198,772,235 preferential buyer's credit (PBC) agreement [China Eximbank PBC No (2015) 39 Total No (382)] for Phase 1 of the Solo-Kertosono Toll Road Project. The PBC, which has a closing date of December 29, 2020, carries the following borrowing terms: a 3% interest rate, a 15-year grace maturity, a 5 year grace period, a 0.2% management fee, and a 0.2% commitment fee. The proceeds of the PBC were to be used by the borrower to partially finance a $237 million commercial (EPC) contract between the Government of Indonesia’s Ministry of Public Works and Housing and China Road and Bridge Corporation (CRBC), which was signed on August 21, 2015. The purpose of Phase 1 was to construct the two-way four-lane Saradan-Kertosono section of the Solo-Kertosono Toll Road (AH2), which is 38.39 km in length. This project, which is located on the island of Java, also involved the construction of 23 bridges in 15 locations with a total length of 659 meters; construction of 1.32 km of access roads; construction of 9 overpasses and 29 underpasses; construction of 1 interchange; and construction of 1 pedestrian bridge. CRBC and Indonesia's WIKA and PP companies were jointly responsible for project implementation. They originally anticipated a project implementation period of 1095 days. However, construction began in April 2015 and a project completion ceremony took place on December 20, 2018.

Staff comments

1. The Chinese project title is 印尼梭罗至卡托索诺收费公路 or 印尼梭罗至卡托索诺收费公路一期工. The Indonesia project title is Proyek Toll Road Development of Solo-Kertosono Phase I.