China Eximbank provides $215.6 million preferential buyer's credit loan for Jatigede Dam Project (Linked to Project ID#39375, ID#72360)
Commitment amount
$ 387949707.6967892
Adjusted commitment amount
$ 387949707.7
Constant 2021 USD
Summary
Funding agency [Type]
Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]
Recipient
Indonesia
Sector
Energy (Code: 230)
Flow type
Loan
Level of public liability
Central government debt
Infrastructure
Yes
Category
Project lifecycle
Geography
Description
On September 25, 2007, China Eximbank and the Government of Indonesia signed a $215,615,732.40 preferential buyer's credit (PBC) agreement [China Eximbank PBC No. (14) Total No. (35)] for the Jatigede Dam Construction Project. The PBC carried the following borrowing terms: a maturity of 15 years, a grace period of 6 years, an interest rate of 3.00%, and a 0.20% management fee of $431,231.46. The loan went into effect on November 20, 2007 and its closing date was November 20, 2013. There was a partial cancellation of the loan on December 21, 2013 worth $24,036.98, making $215,591,695.42 the net commitment value, which was fully disbursed. The first principal payment was scheduled for January 21, 2014 and the last principal payment was scheduled for July 21, 2022. The proceeds of the PBC were to be used by the borrower to partially finance a commercial (EPC) contract between Perusahaan Listrik Negara (PLN) — an Indonesian state-owned electricity company — and Sinohydro Corporation Limited, which was signed on April 30, 2007. The purpose of the project was to construct an embankment dam on the Cimanuk River in Sumedang Regency, West Java. It is located 19 km (12 mi) east of the town of Sumedang (exact locational coordinates: 6°51′23″S 108°05′41″E). Upon completion, the dam was expected to provide water to irrigate approximately 90,000 hectares of farmland and help alleviate water shortages and droughts. It expected to benefit over 1 million people. Sinohydro Corporation Limited and a consortium of Indonesian contractors were responsible for project implementation. Donfang Electric Corporation (DEC) was the supplier of two 55 MW water turbine-generator sets. The originally anticipated project implementation period was from November 15, 2007 to September 9, 2016. Construction actually began on October 23, 2008. The Government of Indonesia announced in late 2011 that that dam was 60% complete. Then, in May 2013, the Government of Indonesia announced that the dam was 70% complete. The dam began to fill with water (i.e initial impounding) on August 31, 2015. In December 2019, PLN announced that the 110MW Jatigede hydropower plant, which was funded by a separate China Eximbank loan (captured in Project ID#39375), was expected to start operations in 2020.
Additional details
1. The Chinese project title is 佳蒂格德大坝. 2. The China Eximbank loan that supported this project is not included in the Overseas Development Finance Dataset that Boston University’s Global Development Policy Center published in December 2020. 3. This is part of a total of $200 million in loans to support Indonesia's 3 major infrastructure projects (see Project ID#72360 for umbrella record).
Number of official sources
11
Number of total sources
22
Details
Cofinanced
No
Direct receiving agencies [Type]
Government of Indonesia [Government Agency]
Implementing agencies [Type]
SinoHydro [State-owned Company]
Perusahaan Listrik Negara (PLN) [State-owned Company]
Indonesia Ministry of Public Works and Housing [Government Agency]
Dongfang Electric Corporation (DEC) [State-owned Company]
Loan Details
Maturity
15 years
Interest rate
3.0%
Grace period
6 years
Grant element (OECD Grant-Equiv)
28.2073%