CDB loan for construction of Quijos Hydroelectric Plant (linked to Record ID#69319)

Commitment Year2011Country of ActivityEcuadorDirect Recipient Country of IncorporationEcuadorSectorEnergyFlow TypeLoan

Status

Project lifecycle

Suspended

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2011
Start (actual)
Jan 20, 2012
End (planned)
Dec 31, 2015
First repayment
Dec 31, 2012
Last repayment
Dec 30, 2018

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The Quijos hydroelectric plant is located in the canton of Quijos in Napo Province. More detailed locational information can be found at https://www.recursosyenergia.gob.ec/proyecto-hidroelectrico-quijos/ and https://www.recursosyenergia.gob.ec/quijos/ and https://www.celec.gob.ec/cocacodosinclair/index.php/2015-09-07-17-45-09/headers/quijos and https://www.openstreetmap.org/way/538793609

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • China Development Bank (CDB)

Receiving agencies

Government Agencies

  • Government of Ecuador

Implementing agencies

Government Agencies

  • Government of Ecuador

State-owned companies

  • China National Electric Engineering Co., Ltd. (CNEEC)

Loan desecription

CDB loan for construction of Quijos Hydroelectric Plant (linked to Record ID#69319)

Grace period2 yearsGrant element9.8429%Interest rate (t₀)7.159%Interest typeFixed Interest RateMaturity8 years

Narrative

Full Description

Project narrative

The Quijos hydroelectric plant project was funded through a 2011 China Development Bank loan of $2,052,360,403.03 (Record ID#35930), specifically through the $1.4 billion discretionary component (Tranche A; Record ID#69319). The loan terms of Tranche A have been applied to this project. In 2011, the Corporation Electrica del Ecuador (CELEC) awarded the 95.5 million USD contract to CNEEC to build the Quijos hydroelectric power plant. Celec awarded China National Electric Equipment Corp. (CNEEC) a US$94.7 million contract in December for construction and equipping of Quijos, to be complete by December 2015. However, by the end of 2015, the contract with CNEEC was terminated. State-owned CELEC submitted its first request to the Public Procurement Service (Sercop) to include the Chinese company in the register for faults in a contract for construction, installation and commissioning of the 50 MW Quijos hydroelectric project. A seven year mediation between CNEEC and CELEC failed. The purpose of this project was to construct a run-of-river 50 mw hydroelectric power plant making use of the Papallacta’s and Quijos’ Rivers water flows. Sand traps would be built to conduct water through connection channels towards recharge wells. The powerhouse was to be equipped with three Francis turbines as well as valves and control panels. The dam was intended to contribute to Ecuador's energy stabilization and sustainability. An environmental impact assessment was conducted and a report was prepared for the UNFCCC CDM. Construction began January 20, 2012. As of January 2017, the project was reported 46% completed. In 2024, reports emerged that construction had been halted since 2016, and previously constructed elements have deteriorated significantly. This deterioration has allegedly caused environmental damage to the area. The area has also been affected by drought that would reduce feasibility of the project.

Staff comments

1. A CELEC project summary released in 2014 put the total project cost at 155,437,705.11 USD. 2. It is unclear how much of the total project cost was financed by CDB- as a result the transaction amount is left blank, and the financing for this project is captured within the total amount of financing recorded for the overall facility (see record #69319).