China Eximbank provides $219.3 million preferential buyer's credit for Phase 2 of Cileunyi-Sumedang-Dawuan Toll Road Project (Linked to Record ID#61325, #61397)

Commitments (Constant USD, 2023)$239,302,764
Commitment Year2016Country of ActivityIndonesiaDirect Recipient Country of IncorporationIndonesiaSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jun 13, 2016
Start (actual)
Nov 29, 2012
End (planned)
Jan 1, 2021
End (actual)
Feb 1, 2023
First repayment (originally scheduled)
Jun 12, 2021
Last repayment (originally scheduled)
Jun 10, 2031

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The Cileunyi-Sumedang-Dawuan Toll Road — also known as the Cisumdawu Toll Road — is a road that, upon completion, will pass through Cileunyi, Tanjung Sari, Sumedang, Cimalaka, Legok, Ujung Jaya and Kertajati. It will connect Padaleunyi Toll Road with Palimanan-Kanci Toll Road. It will also connect Bandung with Kertajati International Airport, which opened in 2018. The road is being built in 6 sections. Section I (or Phase 1): Cileunyi–Tanjungsari (12.0 km); Section II (or Phase 2): Tanjungsari–Sumedang (17.5 km); Section III (or Phase 3): Sumedang–Cimalaka (3.7 km); Section IV (or Phase 4): Cimalaka–Legok (7.2 km); Section V (or Phase 5): Legok–Ujungjaya (15.9 km); and Section VI (Phase 5): Ujungjaya–Dawuan (4.0 km). This project captures the 17.5 km road segment from Tanjungsari to Sumedang (Section II). More detailed locational information can be found at https://www.openstreetmap.org/way/636485855#map=14/-6.8564/107.8708 and https://www.openstreetmap.org/way/782134017 and https://www.openstreetmap.org/way/578346300 and https://www.openstreetmap.org/way/636485849 and https://www.openstreetmap.org/way/714614251

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Indonesia

Implementing agencies

Government Agencies

  • Indonesia Ministry of Public Works and Housing

State-owned companies

  • China MCC17 Group Co., LTD
  • MCC Overseas Ltd (MCCO)
  • PT Waskita Karya (Persero) Tbk
  • PT Wijaya Karya Tbk (Wika)
  • Shanghai Construction Engineering Group (SCG) (上海建工)

Loan desecription

China Eximbank provides $219.3 million preferential buyer's credit for Phase 2 of Cileunyi-Sumedang-Dawuan Toll Road Project

Grace period5 yearsGrant element41.4363%Interest rate (t₀)3%Interest typeFixed Interest RateMaturity15 years

Narrative

Full Description

Project narrative

On June 13, 2016, China Eximbank and the Government of Indonesia signed a $219,398,580 preferential buyer's credit (PBC) agreement [CHINA EXIMBANK PBC NO (2015) TOTAL NO (389)] for Phase 2 of the Cileunyi-Sumedang-Dawuan Toll Road Project (captured in Record ID#39363). The PBC, which went into effect on September 30, 2016, carried the following terms: 15-year maturity, 3-year grace period, 3% interest rate, 0.2% commitment fee, and 0.2% management fee. The closing date of this PBC agreement is June 13, 2021. Funding for Phase 1 of the Cileunyi-Sumedang-Dawuan Toll Road was signed on November 12, 2012 between the China Exim Bank and the Government of Indonesia worth $92,999,886.66 in preferential buyer's credit (PBC) [CHINA EXIMBANK PBC NO. (2012) 35 TOTAL NO. (223)] (captured in Record ID#61325). The PBC, which went into effect on March 11, 2013, carried the following terms: 15-year maturity, 3-year grace period, 3% interest rate, and 0.2% management fee. On March 3, 2016, the closing date of the PBC agreement was extended from March 11, 2016 to August 28, 2017. Then, on August 28, 2017, the PBC agreement was again extended from August 28, 2017 to December 21, 2017. As of December 21, 2017, $84,693,920 of the $92,999,886.66 PBC had been disbursed. On May 7, 2018, China Eximbank and the Government of Indonesia signed a $130,387,425.76 preferential buyer's credit (PBC) agreement for Phase 3 of the Cileunyi-Sumedang-Dawuan Toll Road Project (captured in Record ID#61397). The Cileunyi-Sumedang-Dawuan Toll Road — also known as the Cisumdawu Toll Road — is a road that, upon completion, will pass through Cileunyi, Tanjung Sari, Sumedang, Cimalaka, Legok, Ujung Jaya and Kertajati. It will connect Padaleunyi Toll Road with Palimanan-Kanci Toll Road. It will also connect Bandung with Kertajati International Airport, which opened in 2018. The road is being built in 6 sections. Section I (or Phase 1): Cileunyi–Tanjungsari (12.0 km); Section II (or Phase 2): Tanjungsari–Sumedang (17.5 km); Section III (or Phase 3): Sumedang–Cimalaka (3.7 km); Section IV (or Phase 4): Cimalaka–Legok (7.2 km); Section V (or Phase 5): Legok–Ujungjaya (15.9 km); and Section VI (Phase 5): Ujungjaya–Dawuan (4.0 km). A consortium of Chinese and Indonesian companies — including the Shanghai Construction Group, Wijaya Karya and Waskita Karya — are responsible for building all the sections of the toll road. However, the Indonesian Ministry of Public Works and Housing, China MCC17 Group Co Ltd, and MCC Overseas Ltd are also involved in project implementation. A formal project commencement ceremony took place on November 29, 2012. In March 2019, construction progress was at 63.42%, and in June 2019 the project was still under implementation. The expected project completion date is 2021. In February 2022, phase two was completed.

Staff comments

1. This project is also known as the Cisumdawu Toll Road Project. The Chinese project title is 万隆高速路 or 又称芝苏达乌公路 or 团印尼芝苏达乌公路项目.