China Eximbank provides $240.9 million preferential buyer's credit for 200MW Takalar Steam Coal Power Plant Construction Project

Commitments (Constant USD, 2023)$247,141,546
Commitment Year2014Country of ActivityIndonesiaDirect Recipient Country of IncorporationIndonesiaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Dec 22, 2014
Start (actual)
May 4, 2015
End (actual)
Jul 2, 2018
First repayment
Dec 21, 2019
Last repayment
Dec 18, 2029

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project was to construct a power plant — with two 100MW power generation units — in Punagaya village within Bangkala District, Jeneponto Regency, South Sulawesi Province (locational coordinates: -5.6236347, 119.550822). More detailed locational information can be found at https://www.openstreetmap.org/way/905955777

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Indonesia

State-owned companies

  • PT Perusahaan Listrik Negara (Persero) (PLN)

Implementing agencies

State-owned companies

  • China Gezhouba Group Company Ltd. (CGGC)

Loan desecription

China Eximbank provides $240.9 million preferential buyer's credit for 200MW Takalar Steam Coal Power Plant Construction Project

Grace period5 yearsGrant element41.4363%Interest rate (t₀)3%Interest typeFixed Interest RateMaturity15 years

Narrative

Full Description

Project narrative

On December 22, 2014, the Export-Import Bank of China signed a $240,983,647 preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC No. (2014) 35 Total No.(329)] with the Government of Indonesia for the 200MW Takalar Steam Coal Power Plant Construction Project. The PBC carried the following borrowing terms: a 3% interest rate, a 15-year grace maturity, and a 5 year grace period. Then, on March 5, 2015, the Government of Indonesia signed a $240,983,647 subsidiary loan agreement [SLA-1260/DSMI/2015] with Perusahaan Listrik Negara (PLN) — an Indonesian state electricity distribution company — for the same project. The proceeds of the loan were to be used by PLN to partially finance an EPC contract with China Gezhouba Group Corporation (CGGC). The purpose of the project was to construct a power plant — with two 100MW power generation units — in Punagaya village within Bangkala District, Jeneponto Regency, South Sulawesi Province (locational coordinates: -5.6236347, 119.550822). CGGC was the EPC contractor responsible for project implementation. Construction commenced on May 4, 2015. The first power generation unit was put into commercial operation on December 19, 2017 and commissioned on December 28, 2017. The second power generation unit was put into commercial operation on February 14, 2018 and commissioned during the same month. Then, on July 2, 2018, a project completion ceremony was held. The project was implemented smoothly, although there were licensing problems namely because of the delay of the issuance of the Liquid Waste Disposal Permit (IPLC), which was only issued by the Ministry of Environment and Forestry on February 19, 2019. Furthermore, crime negatively impacted the project, with the theft of ground cables in the switchyard area of the Punagaya Main Substation (GI) .

Staff comments

1. The project is also known as the 2x100MW Takalar Steam Coal Power Plant Construction Project or Punagaya FTP2. The Indonesia project title is Proyek Takalar. The Chinese project title is 塔卡拉燃煤电站项目.