Skip to content

Overview

ICBC provides $825 million export credit facility for 600MW Morupule B Power Plant Construction Project (Linked to Record ID#98173)

Commitments (Constant USD, 2023)$1,144,604,527
Commitment Year2009Country of ActivityBotswanaDirect Recipient Country of IncorporationBotswanaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jun 15, 2009
Start (planned)
Apr 29, 2009
Start (actual)
Feb 19, 2010
End (planned)
Oct 1, 2012
End (actual)
May 4, 2014
First repayment
Dec 13, 2012
Last repayment
Jun 10, 2029

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The Morupule B Power Station is located near the town of Palapye within the Central Province. It is geographically adjacent to the existing Morupule A Power Station. More detailed locational information can be found at https://www.gem.wiki/Morupule_B_power_station and https://www.google.com/maps/place/Morupule-B+power+station/@-22.5218537,27.0482263,15z/data=!4m2!3m1!1s0x0:0xab690215c7537cd8?sa=X&ved=2ahUKEwjG86b-hN_rAhXUlXIEHf8EA_kQ_BIwE3oECBIQCA and https://www.openstreetmap.org/way/316499815#map=19/-22.52041/27.03921 and http://globalenergyobservatory.org/geoid/4377.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Commercial Banks

  • Industrial and Commercial Bank of China (ICBC)

Cofinancing agencies

Intergovernmental Organizations

  • African Development Bank (AfDB) (ADB) (BAD)
  • World Bank

Private Sector

  • Standard Bank

Receiving agencies

State-owned companies

  • Botswana Power Corporation

Implementing agencies

Private Sector

  • Shenyang Boiler Works

State-owned companies

  • Botswana Power Corporation
  • China National Electric Engineering Co., Ltd. (CNEEC)
  • Shenyang Blower Works (Group) Co., Ltd

Guarantors

Government Agencies

  • Botswana Ministry of Finance and Economic Development

Insurance providers

Intergovernmental Organizations

  • World Bank

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Collateral providers

Government Agencies

  • Government of Botswana

State-owned companies

  • Botswana Power Corporation

Loan desecription

ICBC provides $825 million export credit facility for 600MW Morupule B Power Plant Construction Project

Grace period3.5 yearsGrant element45.6209%Interest rate (t₀)2.76875%Interest typeVariable Interest RateLoan tenor6-month rateMaturity20 years

Collateral

The loan was collateralized against a cash deposit in a Debt Service Reserve Account (DSRA) equivalent to one semi-annual principal and interest payment worth $33 million (in September 2018). In the event that Botswana Power Corporation uses funds in the DSRA to make principal or interest payments, it is required to replenish the DSRA within 2 working days. The cash balance of the DSRA was $33 million in 2019, $33 million in 2020, and $33 million in 2021.

Narrative

Full Description

Project narrative

On June 15, 2009, the Industrial and Commercial Bank of China (ICBC) and Botswana Power Corporation (BPC) — a state-owned power company in Botswana — signed a $825,048,559.40 export credit facility agreement for the 600MW Morupule B Power Plant Construction Project. The loan carries the following borrowing terms: a 20-year maturity, a 3.5-year grace period, and an annual interest rate of 6-month LIBOR plus a 1.6% margin. The borrower was expected to repay the loan between December 2012 to June 2029. It was also expected to use the loan proceeds to finance 85% of the cost of a $970 million commercial (EPC) contract with China National Electric Equipment Corporation (CNEEC), which was signed in November 2008. Sinosure and World Bank insured the buyer's credit loan (export credit facility) and the Government of Botswana’s Ministry of Finance also provided a sovereign guarantee. As an additional credit enhancement, the borrower agreed to maintain a minimum cash balance of $33 million (equivalent to one principal and interest repayment/installment) in a Debt Service Reserve Account (DSRA). The Government of Republic of Botswana funded the DSRA with P300 million while Botswana Power Corporation paid the balance of P48 million. The total cost of the Morupule B Power Project was $1.6623 billion. It was financed according to a 70:30 debt-to-equity ratio. ICBC contributed $825 million of debt financing, while the World Bank, and the African Development Bank contributed $136.4 million and $202.5 million of debt financing, respectively. The 30% equity contribution ($498.4 million) came from Botswana Power Corporation and the Government of Botswana. In addition to the long-term (20-year) export credit facility, ICBC provided a short-term $140 million equity bridge loan to the project sponsor (BPC) to ensure that it could meet its equity contribution requirement. The borrowing terms that applied to the equity bridge loan are unknown. However, it is known that the loan was guaranteed by Standard Bank. Standard Bank also provided 20-year currency and interest rate hedging for the export credit facility – a cross-currency swap designed to convert US dollar funding into fixed rate synthetic Botswana Pula, thus minimizing BPC's exposure to adverse movements in foreign exchange and interest rates, and enabling the sponsor to align loan currency with the currency of its revenue stream for the full repayment period. The project involved the construction of a 600MW coal-fired power plant consisting of 4x150MW units — that uses circulating fluidized bed technology — for domestic power generation purpose. The 600MW Morupule B power plant is located in the township of Palapye, northeast of Gaborone, and it geographically adjacent to the existing 132MW Morupule A power plant. It sources feedstock from the same mine as the existing 132MW Morupule A plant. The project has three main components: the Morupule B Power Station; a 400kV Morupule B–Phokoje transmission system and associated sub-stations linking the plant to the BPC grid; and a 35-borehole well-field and associated water reticulation system. The coal is sourced from the Morupule coal mine, which is the only major operating coal mine in Botswana. The Morupule coal mine is operated by Morupule Colliery Limited, a subsidiary of Debswana Diamond Company. China National Electric Equipment Corporation (CNEEC) was the general EPC contractor responsible for implementation. Shenyang Blower Works (Group) Co., Ltd (SBW) also supported the project as a subcontractor. Site and contractor’s camp accommodation facilities as well as bush clearing activities started in early June 2009 and were effectively completed by the end of July 2009, which facilitated CNEEC-SBW to undertake Topographical Survey and Geotechnical Investigation to confirm the design parameters associated with the in-situ ground geological data at the site area. The erection of the contractor’s camp facilities started in November 2009. The camp had the capacity to accommodate approximately 1,500 staff. The project's official EPC contract commencement date was April 29, 2009. However, the project's groundbreaking ceremony did not take place until February 19, 2010. It was originally envisaged that the power plant plant would become operational by October 2012. However, the project experienced significant delays and CNEEC did not hand over the four power generation units to the BPC until May 4, 2014. Then, in October 2014, three of the four power generation units broke down, and the Government of Botswana had needed to consider importing energy from South Africa. The power plant was originally expected to operate at the annual capacity factor of about 80 percent, with annual gross generation of about 4,200 gigawatt-hour (GWh). However, the plant’s capacity factor was closer to 50 percent, reflecting poor availability and unreliability of the units due to forced outages. Units 1-4 had the capacity to produce 600MW, but they only operated at 21 percent capacity producing only 130MW. According to BPC's 2019 Annual Report, BPC signed a Defects Remediation Agreement with CNEEC to remedy the plant's defects, which was expected to result in the remediation of all plant defects in a phased manner between 2019 and January 2023. Efforts were also undertaken to expand the plant’s power generation capacity to 900MW after a tender for construction of two additional units (Unit 5 and 6) was awarded to a joint venture between Japanese Marubeni and South Korea’s Posco Energy.

Staff comments

1. This project is also known as 4x150 MW Morupule B Power Station Expansion Project or the 600MW Morupule B Coal Power Station Project. The Chinese project title is 博茨瓦纳莫鲁卜勒B燃煤电站项目 or 博Morupule电站建设项目. 2. The database of Chinese loan commitments that SAIS-CARI released in July 2020 does not record the interest rate that applied to the loan. AidData records the interest rate (6-month LIBOR plus a 1.6% margin) that is reported by the borrower (Botswana Power Corporation) and the Government of Botswana. The effective interest rate that applies to this loan (2.78%) was calculated by taking the average 6-month LIBOR rate during the month (June 2009) when the loan agreement was finalized (1.18%) and adding a 1.6% margin. 3. In the event of use of Debt Service Reserve Account to settle a given loan installment, the borrower (Botswana Power Corporation) is required to replenish the account within 2 working days. 4. A December 15, 2009 cooperation agreement between Sinosure and the IBRD can be accessed in its entirety via https://documents1.worldbank.org/curated/en/924801468013745596/pdf/Conformed0Version0Cooperation0Agreement.pdf 5. A useful overview of the partial credit guarantee from the IBRD can be found at https://documents1.worldbank.org/curated/en/209491468227707381/pdf/593910BRI0Bots10Box358280B01PUBLIC1.pdf and https://documents1.worldbank.org/curated/en/392781485213835961/pdf/ICRR-Disclosable-P112516-01-23-2017-1485213819609.pdf 6. The $825.048 million long-term debt was guaranteed by Sinosure (commercial and political risk insurance) for the first 15 years, followed by a partial guarantee from the IBRD/World Bank for the remaining 5 years. Approvals from the World Bank and Sinosure were secured in October 2009. 7. Delphos International served as a financial adviser. Minchin & Kelly served as legal counsel to the project sponsor. Clifford Chance and Armstrongs served as legal counsel to the lender. 8. One source (https://www.ijglobal.com/articles/107957/morupule-b-emergency-powers) claims that the borrower paid a 'liquidity premium of 3% for debt provider ICBC'. More research is needed to determine if this premium refers to the Sinosure insurance premium.