Project ID: 40764

Chinese Government provides $55 million grant for National Athletic and Football Stadium Renovation Project

Commitment amount

$ 64576795.68592148

Adjusted commitment amount

$ 64576795.69

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Grenada

Sector

Other social infrastructure and services (Code: 160)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2012-01-01

Actual start

2013-12-17

Actual complete

2015-12-17

Geography

Description

In April 2013, the government of Grenada said China had earmarked $31.49 million for the rebuilding of National Athletic and Football Stadium. The 18-month stadium project will include a complete redo of the football field and athletics track and 7,000 permanent seats, in addition to the existing bleachers. When completed, the stadium will include a pyramid shaped roof, a new eight lane Mondo track and aspects of 'green technology'. The stadium will replace the current structure, which was severely damaged by Hurricane Ivan in 2004. Subsequent reports indicated that the project itself cost EC $68 million ($25.19 million USD). According to a 2017 Government of Grenada source, China provided 10 million USD in 2012 to the Athletic stadium, 30 million USD in 2014, 15 million USD in 2015. The total of 55 million USD has been captured as the transaction amount. According to the 2016 estimates of revenue and expenditure, the form of financing is a grant. A ground-breaking ceremony was held on December 17, 2013. According to the 2016 estimates of revenue and expenditure, construction works on this Chinese grant funded Project commenced in early 2014 and was expected to be completed in 18-24 months at an estimated cost of approximately $64.8 million. The project is now completed and will be handed over to the Government in the first quarter of 2016. The estimated cost of works undertaken during the course of 2015 is $15.0 million. China State Construction Engineering Company (CSCEC) finished construction on October 15, 2015, and the stadium was officially handed over on January 23, 2016.

Additional details

Not to be confused with project #39889

Number of official sources

5

Number of total sources

7

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Grenada [Government Agency]

Implementing agencies [Type]

China State Construction Engineering Corporation (CSCEC) [State-owned Company]