Skip to content

Overview

Chinese Government provides RMB 5 million grant for Goce Delcev Primary School Renovation Project

Commitments (Constant USD, 2023)$1,015,382
Commitment Year2009Country of ActivityNorth MacedoniaDirect Recipient Country of IncorporationNorth MacedoniaSectorEducationFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Aug 10, 2009
Start (actual)
May 14, 2010
End (actual)
Aug 10, 2010

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of this project was to renovate the Goce Delčev primary school (ООУ Гоце Делчев) in the municipality of Prilep. More detailed locational information can be found at https://www.openstreetmap.org/way/860988445#map=18/41.34306/21.56782.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of North Macedonia

Implementing agencies

Government Agencies

  • Government of North Macedonia

Private Sector

  • B.A.R. ECE

State-owned companies

  • China IPPR International Engineering Co., Ltd.

Loan desecription

Chinese Government provides RMB 5 million grant for Goce Delcev Primary School Renovation Project

Narrative

Full Description

Project narrative

On August 6, 2009 and August 10, 2009, the Chinese Government and the Government of Macedonia signed letters of exchange, committing RMB 5 million of grant funding for the Goce Delcev Primary School Renovation Project. The purpose of this project was to renovate the Goce Delcev primary school (ООУ Гоце Делчев) in the municipality of Prilep. It involved the installation of new windows, flooring, and roofing, as well as the provision of new benches, stools, and blackboards. China IPPR International Engineering Co., Ltd. (IPPR) was the contractor responsible for implementation. It hired a Macedonian firm (B.A.R. ECE) as a subcontractor on January 30, 2010. The project commenced on May 14, 2010, and ended on August 10, 2010. It was officially handed over to the local authorities on November 12, 2010.

Staff comments

This project is also known as the Goce Delčev Primary School Renovation Project. The Macedonian project title is проект за реновирање на ОУ Гоце Делчев во Прилеп. The Chinese project title is 援马其顿学校整修项目. According to the subcontractor responsible for construction, the monetary value of the grant commitment that supported this project is RMB 4,720,000.