Project ID: 42473

Chinese Government provides RMB 150 million grant — via ETCA — for Student Dormitory Construction Project

Commitment amount

$ 27518963.463324104

Adjusted commitment amount

$ 27518963.46

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Belarus

Sector

Education (Code: 110)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2013-07-16

Actual start

2016-07-26

Planned complete

2018-01-01

Actual complete

2019-10-11

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On August 13, 2012, the Chinese Government and the Government of Belarus signed letters of exchange regarding a feasibility study for the Student Dormitory Construction Project. Then, on July 16, 2013, the Chinese Government and the Government of Belarus signed an Economic and Technical Cooperation Agreement (ETCA), committing RMB 150 million of grant funding for the Student Dormitory Construction Project. China’s Ministry of Commerce (MOFCOM) was the source of of funding. however, its funding was channeled through a bank account that the Government of Belarus had established with China Development Bank (CDB). The purpose of the project was to construct a dormitory (“hostel”) at Belarusian National Technical University (BNTU) capable of accommodating 1,030 Chinese and Belarusian students. The dormitory is located in the capital city of Minsk and it is located within the boundaries of Dzerzhinsky Avenue and the streets of Semashko and Čiurlionis. The ground floor includes public catering facilities, outpatient clinics, administrative premises, premises for cultural events and consumer services, and fitness facilities. China Railway 25th Bureau Group Co Ltd. was the contractor responsible for project implementation. A formal groundbreaking ceremony took place on April 28, 2016. However, project implementation did not commence until July 26, 2017. It was originally anticipated that the project would reach completion by January 1, 2018. However, it was ultimately completed on July 25, 2018. A project handover certificate was issued in August 2018. The grand opening of the new dormitory took place on October 11, 2019. Additional financing for this project came from a supplemental MOFCOM grant (captured in Project ID#66274). According to various media articles, the total financing for this project was $40 million, which is slightly less than the sum of the RMB 150 million grant commitment captured in Project ID #42473 and the supplemental RMB 200 million RMB ETCA grant commitment captured in Project ID #66274.

Additional details

This project is also known as the Belarusian National Technical University Student Dormitory Construction Project and the Student Village Complex Construction Project. The Russian project title is строительство студенческого общежития or проекта «Строительство студенческого общежития» or комплекса «Студенческая деревня» or Студенческая деревня. The Chinese project title is 援白俄罗斯大学生公寓楼工程.

Number of official sources

6

Number of total sources

22

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Belarus [Government Agency]

Implementing agencies [Type]

China Railway 25th Bureau Group Co.,Ltd. [State-owned Company]