Chinese Government provides RMB 32 million grant for Rajko Zinzifov Primary School and Sports Hall Construction Project

Commitments (Constant USD, 2023)$5,625,737
Commitment Year2011Country of ActivityNorth MacedoniaDirect Recipient Country of IncorporationNorth MacedoniaSectorEducationFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2011
Start (actual)
Nov 1, 2012
End (actual)
Jun 21, 2019

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of this project was to construct the Rajko Zinzifov Primary School (School ОУ Рајко Жинзифов) — capable of accommodating 800 students — in the Dracevo settlement within the municipality of Kisela Voda. More detailed locational information can be found at https://www.openstreetmap.org/way/177490041.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of North Macedonia

Implementing agencies

Private Sector

  • B.A.R. ECE
  • LINKIA

State-owned companies

  • China IPPR International Engineering Co., Ltd.

Loan desecription

Chinese Government provides RMB 32 million grant for Rajko Zinzifov Primary School and Sports Hall Construction Project

Narrative

Full Description

Project narrative

In November 2011, the Chinese Government and the Government of Macedonia signed letters of cooperation, committing RMB 32 million (EUR 3.9 million) of grant funding for the Rajko Zinzifov Primary School Construction Project. The purpose of this project was to construct the Rajko Zinzifov Primary School (School ОУ Рајко Жинзифов) — capable of accommodating 800 students — as well as a sports hall in the Dracevo settlement within the municipality of Kisela Voda. The school has 35 classrooms and it is equipped with modern equipment and a library. It also has a football field, basketball court, athletics track. The project was designed by a Chinese state-owned company called China IPPR International Engineering Co., Ltd. (IPPR). However, it was implemented by two Macedonian companies called B.A.R. ECE and LINKIA. A foundation stone laying ceremony took place on November 11, 2012 and the originally expected completion date of the project was November 1, 2013. However, the school did not officially open its doors until September 1, 2014. The other part of the project is the construction new gymnasium and teaching building was built with Chinese funding in 2019. A handover ceremony was held on June 21st, 2019 for the renovation. The new gymnasium has an area of 588m2 and consists of a multi-purpose hall - for volleyball, basketball, handball, gymnastics and auxiliary rooms: wardrobe, sanitary facilities with showers, a trainer's room together with a sanitary section and a storage area for props.

Staff comments

This project is also known as the Rajko Zhinzifov Primary School Construction Project and the Kisela Voda Primary School Construction Project. The Macedonian project title is изградба на нова училишна зграда за ОУ “Рајко Жинзифов."; the Chinese name for the project is 拉伊科·津基福中国-北马其顿友谊初级学校