Project ID: 47031

China Eximbank provides $690.7 million preferential buyer’s credit loan for 113km Thiès-Touba Toll Road Project

Commitment amount

$ 775188224.6636462

Adjusted commitment amount

$ 775188224.66

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Senegal

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2015-06-08

Actual start

2016-01-16

Actual complete

2018-12-20

Geography

Description

On June 8, 2015, China Eximbank and the Government of Senegal signed a preferential buyer’s credit (PBC) agreement worth USD 690,728,949 for the Thiès-Touba Toll Road Project. The PBC reportedly carries the following terms: a 25-year maturity, a 5-year grace period, and a 2% interest rate. The purpose of this loan was to cover 85% of the total project cost equal to $812 million. This project involved the construction of a 112.933 km, four-lane, toll road between the city of Touba and the city of Thiès and the installation of tolling and video surveillance equipment. The purpose of the project was to connect two of the country’s primary growth areas by linking Touba, Senegal’s second-largest city, with the existing highway network in Thiès, on the perimeter of Dakar, the country’s dominant urban area. The road was designed to conform with French codes and standards. CCCC First Highway Consultants Co. Ltd. was responsible for the design of the project. China Road and Bridge Corporation (CRBC), a subsidiary of China Communications Construction Company, was the general contractor responsible for project implementation. CCCC First Navigation Engineering Bureau Co., Ltd. also served as subcontractor. The project commenced on January 16, 2016 and it was originally anticipated that the project would reach completion within 45 months (with a defect liability period of 12 months). However, the road was ultimately completed opened for traffic on December 20, 2018. Then, on February 1, 2019, the road officially began toll operations.

Additional details

1. This project is also known as the Ilaa Touba Highway Project, the Thiès-Touba Toll Highway Project, and the Thiès-Touba Toll Expressway Project. The Chinese project title is 建的捷斯—图巴高速公路项目. The French project title is Le projet de construction de l'autoroute Thiès-Touba.

Number of official sources

29

Number of total sources

35

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Senegal [Government Agency]

Implementing agencies [Type]

China Road & Bridge Corporation (CRBC) [State-owned Company]

CCCC Highway Consultants Co., Ltd. (中交公路规划设计院有限公司) [State-owned Company]

CCCC First Navigation Engineering Bureau Co., Ltd. [State-owned Company]

Loan Details

Maturity

25 years

Interest rate

2.0%

Grace period

5 years

Grant element (OECD Grant-Equiv)

53.2028%

Bilateral loan

Export buyer's credit

Investment project loan

Preferential Buyer's Credit