Chinese Government provides $19.5 million USD grant for Phase II of Khartoum State Electricity Facilities Rehabilitation Project (Linked to #47128, #57982)
Commitment amount
$ 39623007.16250572
Adjusted commitment amount
$ 39623007.16
Constant 2021 USD
Summary
Funding agency [Type]
China Ministry of Commerce [Government Agency]
Recipient
Sudan
Sector
Energy (Code: 230)
Flow type
Grant
Infrastructure
Yes
Category
Project lifecycle
Geography
Description
In October 2006, the Chinese Government and the Government of Sudan signed a $19.5 million USD grant agreement for Phase II of the Khartoum State Electricity Facilities Rehabilitation Project. China National Electric Engineering Co., Ltd. (CNEEC or 中国电力工程有限公司) was the contractor responsible for implementation. This project was completed, but the precise project start and end dates are unknown. In 2002, China provided two loans for Phase I of this project (see #47128, #57982).
Additional details
This project is also known as the Phase 2 of the National Capital Power Project and Phase 2 of the Khartoum State Electricity Project. The Chinese project title is 苏丹首都电网改造工程.
Number of official sources
2
Number of total sources
3
Details
Cofinanced
No
Direct receiving agencies [Type]
Government of Sudan [Government Agency]
Implementing agencies [Type]
China National Electric Engineering Co., Ltd. (CNEEC) [State-owned Company]
Sudan Ministry of Energy and Mineral Resources [Government Agency]