Chinese Government provides $19.5 million USD grant for Phase II of Khartoum State Electricity Facilities Rehabilitation Project (Linked to Record ID#47128, #57982)

Commitments (Constant USD, 2023)$36,592,064
Commitment Year2006Country of ActivitySudanDirect Recipient Country of IncorporationSudanSectorEnergyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Oct 1, 2006

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to fund Khartoum State Electricity Facilities Rehabilitation Project. More detailed location information can be found at https://www.openstreetmap.org/relation/3774673#map=9/15.9007/33.0133.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Sudan

Implementing agencies

Government Agencies

  • Sudan Ministry of Energy and Mineral Resources

State-owned companies

  • China National Electric Engineering Co., Ltd. (CNEEC)

Loan desecription

Chinese Government provides $19.5 million USD grant for Phase II of Khartoum State Electricity Facilities Rehabilitation Project (Linked to Record ID#47128, #57982)

Narrative

Full Description

Project narrative

In October 2006, the Chinese Government and the Government of Sudan signed a $19.5 million USD grant agreement for Phase II of the Khartoum State Electricity Facilities Rehabilitation Project. China National Electric Engineering Co., Ltd. (CNEEC or 中国电力工程有限公司) was the contractor responsible for implementation. This project was completed, but the precise project start and end dates are unknown. In 2002, China provided two loans for Phase I of this project (see #47128, #57982).

Staff comments

This project is also known as the Phase 2 of the National Capital Power Project and Phase 2 of the Khartoum State Electricity Project. The Chinese project title is 苏丹首都电网改造工程.