Project ID: 52520

Viru Viru Airport

Not recommended for aggregates

This project is not recommended for use in creating aggregated sums. See the documentation for more information about this criteria.

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Bolivia

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Unallocable

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

Vague (Official Finance) (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Pipeline: Pledge (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-01-01

Description

In 2016, Bolivian President Morales announced the Viru Viru airport project [or Santa Cruz Airport Design and Construction Project] was contracted with Chinese company Beijing Urban Construction. The contracted amount is $300 million USD. Bolivia stressed that the airport will be invested and constructed by the Bolivian government and will become the international passenger and freight logistics center after the completion of the project. The Bolivian government will seek loan support from the Export-Import Bank of China for the project. Therefore, after the project is signed, the construction plan will also need to be evaluated by the Chinese financial institution. Viru Viru will include a new runway, three passenger terminals and cargo storage facilities. In March 2017, the export-import bank asked for external evaluation for the airport project. In April 2017, implementation troubles were revealed when Bolivian Vice President Alvaro Garcia warned China EXIM Bank that if it does not speed up the release of funds for the project to transform Viru Viru airport into a new hub, it might be forced to seek alternative financing arrangements. It is not clear whether the bank will approve the money for this project yet.

Additional details

the transaction amount is not included because it is unclear how much Exim bank will loan to this project

Number of official sources

3

Number of total sources

6

Download the dataset

Details

Cofinanced

No

Implementing agencies [Type]

Beijing Urban Construction Group Co., Ltd. [State-owned Company]

Loan Details

Bilateral loan

Investment project loan