Project ID: 52924

Chinese Government provides RMB 489.5 million grant — via ETCA — for Phase 1 of Bishkek Municipal Road Network Reconstruction Project (Linked to Project ID#54376 and #71678)

Commitment amount

$ 86982388.6377354

Adjusted commitment amount

$ 86982388.64

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Kyrgyzstan

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-06-20

Actual start

2017-12-12

Planned complete

2019-09-25

Actual complete

2019-11-04

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On June 20, 2016, letters of exchange were signed by the Chinese Government and the Government of the Kyrgyz Republic for Phase 1 of the Bishkek Municipal Road Network Reconstruction Project. As part of this agreement, the Chinese Government agreed to provide a RMB 489.5 million grant for Phase 1, which involved the construction of 7 bridges and the the restoration of 49 streets in Bishkek (measuring 95 kilometers in length). The grant funding was drawn in part from an Economic and Technical Cooperation Agreement (ETCA) that the Chinese Government and the Government of the Kyrgyz Republic signed in May 2018. The proceeds of the grant were to be used to finance a commercial contract between China Road and Bridge Corporation (CRBC) and Bishkek Municipal Infrastructure Construction Authority, which was signed on September 16, 2016. China Road and Bridge Corporation (CRBC) was the contractor responsible for project implementation. A formal groundbreaking ceremony took place on began in October 2016. However, construction began approximately six months earlier — on December 12, 2017. As part of Phase 1, Manas Street was re-opened on August 25, 2018. Phase 1 was ultimately completed nearly 40 days ahead of schedule (September 25, 2019) on November 4, 2019. An official handover ceremony took place on October 19, 2021. Then, on March 4, 2022, a project completion (handover) certificate was issued. The Chinese Government also provided an RMB 278.73 million grant for the project’s second phase (captured via Project ID#54376). The May 2018 ETCA is captured via Project ID#71678.

Additional details

1. This project is also known as Phase 1 of the Bishkek Asphalt Pavement Rehabilitation Project. The Russian project title is 1 фаза проекта «Развитие улично-дорожной сети города Бишкек». The Chinese title is 吉尔吉斯斯坦比什凯克市政路网改造(一期). 2. Some sources refer to the face value of the grant as RMB 481 million rather than RMB 489.5 million. This issue warrants further investigation.

Number of official sources

21

Number of total sources

47

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of the Kyrgyz Republic [Government Agency]

Implementing agencies [Type]

China Road & Bridge Corporation (CRBC) [State-owned Company]

Government of the Kyrgyz Republic [Government Agency]