Project ID: 53038

China Eximbank provides $127.5 million preferential buyer's credit for Phase I of Lusaka-Kafue Bulk Water Supply Project (Linked to Project ID#98552)

Commitment amount

$ 150552574.81570455

Adjusted commitment amount

$ 150552574.82

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Zambia

Sector

Water supply and sanitation (Code: 140)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-05-01

Actual start

2016-09-05

Planned complete

2018-11-01

Actual complete

2019-06-01

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In May 2016, China Eximbank and the Government of Zambia signed a $127.5 million preferential buyer's credit (PBC) agreement for the Phase I of Lusaka-Kafue Bulk Water Supply Project. The borrowing terms of the PBC are unknown. However, it is known that the borrower was expected to use the proceeds from the PBC to finance 85% of a $150 million commercial contract between Lusaka Water and Sewerage Company (LWSC) and China Civil Engineering Construction Corporation (CCECC) Zambia Limited, which was signed in January 2013. The Government of Zambia agreed to directly finance the remaining 15% ($22.5 million) of the commercial contract cost. The project involved the construction of a new raw water abstraction station on the Kafue River, a water treatment plant, a 66 km treated water pipeline from Kafue to Lusaka, and a booster station in Chilanga and transmission lines to deliver a total of 50,000m3/day of water into the existing Stuart Park storage facilities in Lusaka. The ultimate objective of the project was to improve water supply to Lusaka and surrounding areas. Upon completion, the project was expected to benefit 480,000 people in Lusaka and surrounding areas. China Civil Engineering Construction Corporation (CCECC) Zambia Limited was the EPC contractor responsible for project implementation. Its work was overseen by Lusaka Water and Sewerage Company (LWSC). A formal groundbreaking ceremony took place on July 20, 2016. However, construction did not begin until September 5, 2016. It was originally anticipated that the project would be completed by November 2018. However, this did not occur due to delays in the delivery of water distribution pipelines. The scope of the project was also revised during implementation to include additional works involving the construction of the Iolanda intake structure (at the Iolanda water treatment plant) and the installation of the Chilanga Booster Pump to meet the power requirements of the project. On September 17, 2020, the President of Zambia visited the project site and affirmed the construction quality and progress of the project. As of December 2020, the project had achieved a 96% completion rate. On July 29, 2022, a project completion ceremony took place. At the ceremony, Zambian president Hakainde Hichilema said that the completion of the project would ensure that about 500,000 people in the Zambian capital have access to clean and safe water as well as proper sanitation. Eric Ding, the general manager of the CCECC Zambia, thanked the Zambian government and the local people for their support during the construction period. He, however, said more financing will be required to undertake the second phase of the project to increase the water supply to the Zambian capital due to the increased population which requires more water. 1,000 local residents were reportedly employed and trained at the peak of the construction phase of the project. China Eximbank and Zambia’s Ministry of Water Development, Sanitation, and Environmental Protection also signed a $79,982,494.00 term loan facility agreement for the Kafue Bulk Water Supply Power Substations Project circa 2019 (see linked ProjectID #98552). The borrowing terms of the loan are unknown. The purpose of the project is to construct electricity substations (transformers) and additional works to support the newly constructed facilities at the Kafue Bulk Water Supply Project. The electricity substations were originally scheduled for installation by February 2020. However, they were not delivered on time for unspecified reasons.

Additional details

1. This project is also known as the Kafue Bulk Water Supply Project Phase I. The Chinese project title was 赞比亚卡夫河供水项目 or 的卡夫河供水项目 or 赞比亚卡夫拉夫塔供水项目 or 卡富埃河供水项目.

Number of official sources

17

Number of total sources

34

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Zambia [Government Agency]

Implementing agencies [Type]

China Civil Engineering Construction Corporation (CCECC) [State-owned Company]

Loan Details

Bilateral loan

Export buyer's credit

Investment project loan

Preferential Buyer's Credit