Project ID: 53182

China Eximbank provides $70.6 million loan for Foundiougne Toll Bridge Construction Project

Commitment amount

$ 83369914.7160425

Adjusted commitment amount

$ 83369914.72

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Senegal

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

Vague (Official Finance) (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-01-01

Actual start

2018-02-20

Planned complete

2020-03-01

Actual complete

2022-01-16

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In 2016, China Eximbank and the Government of Senegal signed a $70,604,333 loan agreement for the Foundiougne Toll Bridge Construction Project. The borrowing terms of the loan are unknown. The borrower was expected to use the proceeds of the loan to finance a $71.04 million commercial (EPC) contract with China Great Wall Industry Group Co., Ltd. and China Henan International Cooperation Group Co., Ltd. The Government of Senegal also provided counterpart funding for this project. According to the Government of Senegal’s Aid Management Platform, as of May 2022, the China Eximbank loan achieved an 80.4% completion rate (with three disbursements taking place in 2018, 2019 and 2020). The project involved the construction of a toll bridge — with a length of 1290 meters, a width of 11.4 meters, and two navigable spans between the piers to facilitate boat traffic — that crosses the Saloum River and connects the cities of Ndakhonga and Foundiougne. The ultimate purpose of the project was to facilitate faster transportation in Senegal's Fatick region and promote the socio-economic development of the Sine-Saloum delta. The bridge is connected to National Road No. 9. China Great Wall Industry Group Co., Ltd. and China Henan International Cooperation Group Co., Ltd were the EPC contractors responsible for implementation. Construction began on February 20, 2018. The bridge was opened to traffic on January 16, 2022. A formal inauguration ceremony took place on March 26, 2022. The bridge was renamed the Nelson Mandela Bridge at the inauguration ceremony. The project reportedly created 2000 direct and indirect jobs. It was originally scheduled to begin implementation in January 2016 and reach completion in September 2019.

Additional details

1. The French project title is le Grand Pont à péage de Foundiougne or Projet de construction du pont de Foundiougne. The Chinese project title is 方久尼大桥项目. 2. The AMP ID number for this project is 872742219534.

Number of official sources

13

Number of total sources

27

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Senegal [Government Agency]

Implementing agencies [Type]

China Great Wall Industry Corporation [State-owned Company]

China Henan International Cooperation Group Co., Ltd. (CHICO) [State-owned Company]

Loan Details

Bilateral loan

Investment project loan