Project ID: 53528

China Eximbank provides RMB 1.636 billion government concessional loan for Kandy North Pathadumbara Integrated Water Supply Project

Commitment amount

$ 279079244.32025224

Adjusted commitment amount

$ 279079244.32

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Sri Lanka

Sector

Water supply and sanitation (Code: 140)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2017-12-22

Actual start

2019-09-21

Planned complete

2022-08-12

Geography

Description

On May 16, 2017, the Chinese Government and the Government of Sri Lanka signed a preferential loan framework agreement for the Kandy North Pathadumbara Integrated Water Supply Project. Then, on December 22, 2017, China Eximbank and the Government of Sri Lanka's Ministry of Finance and Mass Media signed an RMB 1,636,553,500 government concessional loan (GCL) agreement [CHINA EXIMBANK GCL NO. (2017) 07 TOTAL NO. (612)] for the Kandy North Pathadumbara Integrated Water Supply Project (KNPIWSP). The GCL carries an interest rate of 2%, a default (penalty) interest rate of 0%, a maturity of 20 years, a 6-year grace period, a 0.25% commitment fee, and a 0.25% (RMB 4,091,383.75) management fee. The loan went into effect on May 29, 2018. Sri Lanka's Ministry of Finance and Mass Media on-lent the proceeds of the loan to Sri Lanka’s National Water Supply and Drainage Board. The borrower was expected to use the loan proceeds to finance a $254,518,429.03 commercial contract (ID# P&P/DB/PATHADUMBARA/2013) between Sri Lanka’s National Water Supply and Drainage Board and Sinohydro Corporation Limited, which was signed on June 16, 2015. China Eximbank disbursed an unknown amount in 2017 and 2018, RMB 274,817,342.53 in 2019, RMB 349,089,845 in 2020, RMB 346,713,167 in 2021, and RMB 50,798,397.47 in 2022. The loan had achieved a 62.4% disbursement rate (RMB 1,021,418,752 out of RMB 1,636,553,500) as of September 2022. The borrower made no repayments between 2017 and 2021. The loan's amount outstanding was RMB 349,089,845 as of December 31, 2020, RMB 695,803,012 as of December 31, 2021, and RMB 746,601,410 as of June 30, 2022. The objective of the project is to provide a safe pipe-borne water supply facility to six divisions, namely Pathadumbara, Harispattuwa, Akurana, Pujapitiya, Kandy Four Gravets, and Thumpane. The scope of the project includes the construction of a clear water reservoir (2100m3 within the existing water treatment plant), a filtration unit, a flocculation unit, a new pump station, and improvements to existing stations, sludge lagoon, service reservoirs, and pump houses. The project also includes the improvement of existing pump stations and the supply and laying of distribution lines and transmission lines. The project is distributed in 6 administrative areas in the north of Kandy. The construction area is about 318 square kilometers. The main construction content is the laying of 83 kilometers of water supply pipelines, 567 kilometers of water distribution pipelines, 29 pools, and 18 pumping stations. After all the planning of the project is completed, it is expected to meet the domestic water demand of 470,000 people. PowerChina is the contractor responsible for project implementation. As of September 30, 2018, the project had achieved a ‘physical progress’ rate of 4%. The loan agreement had already been finalized at that time, but cabinet approval was needed for deviations in the project scope. Land acquisition and procurement activities were underway. As of December 31, 2018, the project had achieved a 'physical progress rate' of 7.42%. Then, on September 21, 2019, a groundbreaking ceremony took place. As of June 30, 2022, the project had achieved a ‘physical progress’ rate of 79.1%. The project was originally expected to reach completion in August 2022.

Additional details

1. This project is also known as the Kandy North Pathadumbara Integrated WSP. The Chinese project title is 提北部帕特杜玛巴若综合供水工程项. 2. The Government of Sri Lanka loan key number is 2017041. 3. Some official sources suggest that the loan disbursed RMB 74,272,502.44 in 2020 and RMB 264,311,211.33 in 2021. This issue warrants further investigation. 4. The China Eximbank loan agreement can be accessed in its entirety via https://www.dropbox.com/s/a778ddcjkcqr2lm/Sri%20Lanka%202017%20China%20Eximbank%20GCL%20for%20Kandy%20North%20Pathadumbara%20Integratd%20Water%20Supply%20Project.pdf?dl=0.

Number of official sources

15

Number of total sources

20

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Sri Lanka Ministry of Finance [Government Agency]

Indirect receiving agencies [Type]

Sri Lanka National Water Supply and Drainage Board [State-owned Company]

Implementing agencies [Type]

China Hydropower Construction Group [State-owned Company]

Power Construction Corporation of China (POWERCHINA) [State-owned Company]

Loan Details

Maturity

20 years

Interest rate

2.0%

Grace period

6 years

Grant element (OECD Grant-Equiv)

40.3074%

Bilateral loan

Government Concessional Loan

Investment project loan