Skip to content

Overview

China Development Bank provides $102.54 million loan for Thambuttegama Water Supply Project

Commitments (Constant USD, 2023)$109,115,519
Commitment Year2017Country of ActivitySri LankaDirect Recipient Country of IncorporationSri LankaSectorWater Supply And SanitationFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Aug 21, 2017
Start (actual)
Jul 1, 2018
End (planned)
Jun 1, 2022
Last repayment
Feb 15, 2033

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

In September 2014, China Development Bank (CDB) agreed in principle to provide a $400 million loan to Sri Lanka’s National Water Supply and Drainage Board for the implementation of the following water supply projects: Katana Water Supply Project; Thambuttegama Water Supply Project; and Kandy North Water Supply Project. The goal of this project is to provide safe drinking water via pipes to all 45 Grama Niladdhari divisions in Katana Divisional Secretariat covering 50% of the population in the area. To do so, the project will, over 3 years, construct a water intake structure with a capacity of 42,000 m3/day, a water treatment plant of 18,000m3/day, a ground reservoir of 1,500 m3 capacity, a raw water and treated water transmission mains totaling up to an approximate length of 50 Km, elevated towers of 1,500 m3 capacity, a distribution network of 135 KM, and facilities to operate and maintain the water supply scheme. More detailed locational information can be found at https://www.openstreetmap.org/way/406572724

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • China Development Bank (CDB)

Cofinancing agencies

State-owned Banks

  • Bank of Ceylon (BOC)

Receiving agencies

Government Agencies

  • National Water Supply & Drainage Board of Sri Lanka

Implementing agencies

Government Agencies

  • National Water Supply & Drainage Board of Sri Lanka

State-owned companies

  • CATIC China Geo Eng JV

Guarantors

Government Agencies

  • Government of Sri Lanka

Loan desecription

China Development Bank provides $102.54 million loan for Thambuttegama Water Supply Project

Grant element26.0389%Interest rate (t₀)4.40639%Interest typeVariable Interest RateMaturity15.5 years

Narrative

Full Description

Project narrative

In September 2014, China Development Bank (CDB) agreed in principle to provide a $400 million loan to Sri Lanka’s National Water Supply and Drainage Board for the implementation of the following water supply projects: Katana Water Supply Project; Thambuttegama Water Supply Project; and Kandy North Water Supply Project. A proposal made by Dinesh Gunawardena, Minister of Water Supply and Drainage, to proceed with the relevant activities pertaining to the loan arrangements, was approved by Sri Lanka’s Cabinet in September 2014. Then, on August 21, 2017, China Development Bank and Sri Lanka’s National Water Supply & Drainage Board signed a $102.54 million loan agreement [ID#4510201701100001265] for the Thambuttegama Water Supply Project (WSP). This loan carried the following borrowing terms: a 15.5-year maturity (final maturity date: March 6, 2033) and an all-in interest rate of approximately 2.954%. The Government of Sri Lanka issued a sovereign guarantee in support of the loan on October 4, 2017. The borrower was to use the proceeds of the China Development Bank loan to partially finance a $120.5 million commercial contract between Sri Lanka’s National Water Supply and Drainage Board and China National Aero-Technology Import & Export Corporation (AVIC), which was signed in July 2015. The remaining $18 million was to be provided by the Bank of Ceylon, a state-owned commercial bank in Sri Lanka. The principal amount outstanding under the $102.54 million loan was $35.64 million as of December 22, 2022. The purpose of the project is to provide safe drinking water via pipes to all 45 Grama Niladdhari divisions in Katana Divisional Secretariat covering 50% of the population in the area (similar to the CDB-financed Katana Water Supply Project captured via Record ID#53566). It involves the construction of a water intake structure with a capacity of 42,000 m3/day, a water treatment plant of 18,000m3/day, a ground reservoir of 1,500 m3 capacity, raw water and treated water transmission mains totaling up to an approximate length of 50 km, elevated towers of 1,500 m3 capacity, a distribution network of 135 km, and facilities to operate and maintain the water supply scheme. CATIC China Geo Eng JV — a joint venture of China Geo-Engineering Corporation (CGC) and China National Aero-Technology Import & Export Corporation (AVIC) — is the EPC contractor responsible for implementation. The project commenced in July 2018. As of September 30, 2018, it had achieved a ‘physical progress’ rate of 4%. As of early 2021, it had achieved a ‘physical progress’ rate of 61.2%. As of June 30, 2022, it had achieved a ‘physical progress’ rate of 85.23%. The project was originally expected to reach completion in June 2022. However, it encountered problems and delays during implementation. In March 2022, By early 2022, it was clear that the loan was non-performing and China Development Bank suspended loan disbursements. On April 12, 2022, the Government of Sri Lanka announced a ‘pre-emptive’ sovereign debt default, noting that it would suspend debt repayments to all external creditors other than multilateral institutions. Its decision to suspend external debt service reportedly affected all China Development Bank loans with amounts outstanding at the time of the announcement. As of March 2023, the Government of Sri Lanka had accumulated $338 million in arrears to China Development Bank.

Staff comments

1. This project is also known as the ‘Thabuttegama’ Water Supply Project. The Chinese project title is Thambuttegama 供水项目 or 斯里兰卡塔布特嘎玛供水项目. 2. This project is one of the four water supply projects under implementation in Sri Lanka funded by the China Development Bank. The other three projects are: Record ID#54435 (Gampaha, Attanagalla and Minuwangoda Integrated Water Supply Scheme), Record ID#53566 (Katana Water Supply Project), Record ID#53568 (Valachchenai Water Supply Project and Banadarawela, Diyathalawa and Haputhale Water Supply Project). 3. According to a March 2018 news report, Sudath Ratnayake, the Assistant General Manager for the North Central Province from Sri Lanka’s National Water Supply and Drainage Board indicated that the CDB loan for the Thambuttegama Water Supply Project carries an interest rate of LIBOR plus a 1-1.5% margin and a maturity length of 15 years. AidData has estimated the all-in interest rate (2.954%) by adding 1.5% to average 6-month rate LIBOR (1.454%) in August 2017. 4. The loan agreement [ID#4510201701100001265] between China Development Bank and Sri Lanka’s National Water Supply & Drainage Board for the Katana Water Supply Project and the Thambuttegama Water Supply Project was amended and extended on August 26, 2020. However, the substantive changes that were made through this contract revision are unknown. This issue requires further investigation. 5. The 2022 amount outstanding data is drawn from https://www.treasury.gov.lk/api/file/39a16e61-7659-476b-8f18-d969c7a69733 and