CDB provides $607 million buyer's credit loan for Phase II of Shymkent Oil Refinery Reconstruction and Modernization Project (Linked to Record ID#72399)

Commitments (Constant USD, 2023)$645,924,713
Commitment Year2017Country of ActivityKazakhstanDirect Recipient Country of IncorporationKazakhstanSectorIndustry, Mining, ConstructionFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jun 9, 2017
End (actual)
Aug 15, 2018
Last repayment
Jun 6, 2030

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project was to provide a $607 million buyer's credit loan for Phase II of Shymkent Oil Refinery Reconstruction and Modernization Project. More detailed locational information can be found at: https://www.openstreetmap.org/relation/5490319#map=11/42.2604/69.6527.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • China Development Bank (CDB)

Cofinancing agencies

Private Sector

  • Crédit Agricole Corporate and Investment Bank (CACIB) (Crédit Agricole CIB) (Formerly Calyon) (Formerly Crédit Agricole Indosuez (CAI))
  • Deutsche Bank AG
  • MUFG Bank, Ltd. (Formerly Bank of Tokyo-Mitsubishi UFJ, Ltd. (BTMU))
  • Sumitomo Mitsui Banking Corporation (SMBC)

Receiving agencies

Joint Venture/Special Purpose Vehicles

  • PetroKazakhstan Oil Products LLP (PKOP)

State-owned Banks

  • Development Bank of Kazakhstan JSC (Baiterek or DBK)

Implementing agencies

State-owned companies

  • China Petroleum Engineering and Construction Corporation (CPECC)

Accountable agencies

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Insurance providers

State-owned companies

  • China Export & Credit Insurance Corporation (Sinosure)

Loan desecription

CDB provides $607 million buyer's credit loan for Phase II of Shymkent Oil Refinery Reconstruction and Modernization Project

Grant element24.5156%Interest rate (t₀)4.11683%Interest typeVariable Interest RateMaturity13 years

Narrative

Full Description

Project narrative

On June 9, 2017, China Development Bank (CDB) signed a $607 million buyer's credit (facility) loan agreement with the Development Bank of Kazakhstan JSC (DBK) for Phase 2 of the Reconstruction and Modernization of the Shymkent Oil Refinery. DBK then used the proceeds from the CDB loan to on-lend to a project company (special purpose vehicle) called PetroKazakhstan Oil Products LLP (PKOP). The CDB loan facility had a maturity date of April 25, 2030 and carried an interest of rate of 2.7% per annum plus LIBOR. In September 2017 and December 2017, DBK drew down two tranches of $100 million each. Then, in June 2018, DBK drew down a further $65 million, and in May 2020, DBK drew down a further $130 million tranche under the facility agreement. The aggregate principal amount outstanding under the facility agreement was $0 as of June 30, 2017, $386 million as of December 31, 2020, and $368.1 million as of December 31, 2021 PKOP also contributed some of its own funds to support the implementation of the project. Additionally, a Sinosure-backed bank syndicate of Calyon, Sumitomo Mitsui Banking Corporation, Bank of Tokyo-Mitsubishi UFJ, and Deutsche Bank provided additional financing to support the project. The syndicate provided $225 million USD to DBK for on-lending, while Sinosure provided export buyer’s credit insurance. The Export-Import Bank of China pledged $1 billion for the first phase of the modernization of the refinery as captured by linked Record ID#72399. The project sought to increase annual production from 5.25 million to 6 million tons and improve refining levels. After the modernization (including Phase I, the plant was to be more environmentally friendly and able to produce Euro-4 and Euro-5 products. The project also included the construction of a complex of catalytic cracking units with a capacity of 2 million tons a year, an alkali treatment unit, a amine recovery unit, a sour water stripper, a pressure swing absorption unit, a unsaturated LPG desulfurization unit, a saturated LPG desulfurization unit, a sulfur production unit, and a revamping of the CDU of LK-6U complex. China Petroleum Engineering and Construction Corporation (CPEEC) was the general contractor responsible for project implementation. Phase II was completed on August 15, 2018.

Staff comments

1. The shareholders of PetroKazakhstan Oil Products LLP are CNPC Exploration and Development Company Ltd. (50%) and JSC Exploration & Production KazMunayGas (50%). CNPC Exploration and Development Company Ltd. is a subsidiary of PetroChina Company Ltd. and a 50/50 joint venture between PetroChina and CNODC. JSC Exploration & Production KazMunaiGas (EP KMG) is engaged in the production of crude oil at the oil fields in western and southern Kazakhstan, and it is a subsidiary of JSC National Company KazMunayGas. 2. The LIBOR rate was not specified, so the 6-month LIBOR is assumed. In June 2017 the average 6-month LIBOR rate was 1.432%. Therefore, AidData has coded the "all-in" interest rate as 1.432% + 2.7%, or 4.132%. 3. This project is also known as the PKOP LLP Project. The Chinese project title is 哈萨克斯坦奇姆肯特炼厂二期. 4. PKOP is a joint venture between KazMunaiGaz and CNPC, which was created in 2005. 5. The 2020 DBK Annual Report suggests that the maturity length of the loan is 10 years and the interest rate is 2.91%. This issue warrants further investigation.