Project ID: 53635

Chinese Government provides RMB 240 million grant for Kabul University Comprehensive Teaching Building and Auditorium Project (Linked to Project ID #54009, #53640, and #53999)

Commitment amount

$ 42647136.410738505

Adjusted commitment amount

$ 42647136.41

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Afghanistan

Sector

Education (Code: 110)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-01-01

Actual start

2017-10-10

Planned complete

2021-05-01

Actual complete

2022-07-31

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On May 16, 2016, Chinese Premier Li Keqiang and Afghan Chief Executive Officer Abdullah Abdullah signed six bilateral cooperation documents, including an exchange of notes on the Kabul University Comprehensive Teaching Building and Auditorium Project. The Chinese Government committed approximately RMB 240 million in grant funding for this project, which involves the construction on the Integrated Teaching Complex and an auditorium for Kabul University. On October 10, 2017, the commencement ceremony of the construction of the comprehensive teaching building and auditorium of Kabul University in Afghanistan was held in Kabul, the capital of Afghanistan. The Kabul University Comprehensive Teaching Building and Auditorium Project includes an academic lecture hall with 40 classrooms and an auditorium with a capacity of 500 people. It covers a total building area of about 14,100 m2, of which the comprehensive teaching building covers 8,350 m2, the auditorium covers 5,200m2, and the equipment room covers 550 m2. Its contents mainly include the major structures of the buildings, building decorations, an electricity system, a water drainage and supply system, an air-conditioning ventilation system, teaching office equipment installation, indoor furniture and appliances, and outdoor engineering. Upon completion, it will be the largest building of Kabul University. China 19th Metallurgical Corporation (MCC19) is the contractor responsible for project implementation. A project commencement ceremony took place on October 10, 2017. Then, the project passed its mid-term acceptance inspection on December 11, 2018. The project was officially completed on June 27, 2021. However, the building did not go into operation until July 31, 2022. The project’s originally expected completion date was May 2021.

Additional details

1. The Chinese project title is 援阿喀布尔大学综合教学楼和礼堂项目, 喀布尔大学礼堂 or 阿富汗喀布尔大学综合教学楼和礼堂项. 2. For another Chinese government grant for Kabul University, see Project ID#53632.

Number of official sources

15

Number of total sources

28

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Afghanistan [Government Agency]

Implementing agencies [Type]

Kabul University [Miscellaneous Agency Type]

Metallurgical Corporation of China Ltd (MCC) [State-owned Company]