Skip to content

Overview

China Eximbank provides $149.4 million government concessional loan for the 60MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project (Linked to Record ID#38705, 71749, 104309)

Commitments (Constant USD, 2023)$169,768,284
Commitment Year2011Country of ActivityNepalDirect Recipient Country of IncorporationNepalSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Feb 28, 2011
Start (actual)
Nov 23, 2011
End (actual)
Nov 18, 2019
First repayment (originally scheduled)
Feb 27, 2016
Last repayment (originally scheduled)
Feb 22, 2036

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The 60 MW Upper Trishuli 3A Hydroelectric Power Plant is located near Simle village within Kispang Rural Municipality on the borders of the Rasuwa and Nuwakot districts. More detailed locational information can be found at https://goo.gl/maps/2XagFnZz1iTJxFDd9, https://goo.gl/maps/6X1th4giavFWVFDW8, https://www.openstreetmap.org/way/341554256, https://www.openstreetmap.org/way/309114157 and https://www.openstreetmap.org/relation/5143911.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Nepal
  • Nepal Electricity Authority (NEA)

Implementing agencies

Government Agencies

  • Government of Nepal

State-owned companies

  • China Energy Engineering Group Northwest Power Construction Engineering Co., Ltd.
  • China Gezhouba Group Company Ltd. (CGGC)

Loan desecription

China Eximbank provides $149.4 million government concessional loan for the 60MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project

Grace period5 yearsGrant element59.1497%Interest rate (t₀)1.75%Interest typeFixed Interest RateMaturity25 years

Narrative

Full Description

Project narrative

The Government of Nepal requested a $120 million concessional loan from the Government of the People’s Republic of China for the 60 MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project on July 31, 2006. Then, on October 11, 2009, Nepal Electricity Authority (NEA) selected China Gezhouba Group Company Ltd (CGGC) as the project’s EPC contractor with a bidding amount of $89,231,692 (exclusive of VAT). A Memorandum of Understanding (MoU) regarding the loan was signed by the Government of Nepal and the Export-Import Bank of China (China Eximbank) on November 4, 2009. The MOU referenced $200 million: $120 million for the 60MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project and $80 million for other projects. An environmental impact assessment (EIA) report was approved by the Government of Nepal’s Ministry of Environment on August 26, 2010 and forwarded to China Eximbank on August 31, 2010. Then, on February 28, 2011, the Government of Nepal and China Eximbank signed a government concessional loan (GCL) agreement [CHINA EXIMBANK GCL NO. (2011) 9 TOTAL NO. (1399)] worth RMB 640 million (equivalent to approximately $90 million) for the 60 MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project. The borrowing terms of the loan were as follows: a 1.75% interest rate, a 25-year maturity, and a 5-year grace period. The Government of Nepal used the proceeds of the loan to develop an on-lending arrangement (through a ‘Subsidiary Loan Agreement’) with NEA on April 15, 2011. The loan agreement went into effect on June 1, 2011. However, the scope of the project was subsequently expanded and the face value of the loan was increased to $149,378,539. The loan achieved a disbursement rate of at least 66.3% ($99,047,167 out of $149,378,539), with 58 disbursements taking place between June 2011 and June 2021. The loan's amount outstanding was RMB 537,862,139 ($83,124,966) as of July 15, 2021. NEA (the ultimate borrower) was expected to use the proceeds of the loan to finance a commercial (EPC) contract that it signed with China Gezhouba Group Co. Ltd. (CGGC) on May 31, 2010. The Upper Trishuli 3A hydroelectric power plant project involved the construction of a 60 MW run-of-river (ROR) plant with annual energy generation of 460 GWh. More specifically, it involved the installation of a 25 meter high diversion weir, intake, desander, 4.1 km headrace tunnel, surge shaft, inclined shaft, underground powerhouse, tailrace, switchyard, 48 km long 220 Kv transmission line, and a 4 circuit 1 km 220 Kv underground cabling and ancillary structure. The power plant is located near Simle village within Kispang Rural Municipality on the borders of the Rasuwa and Nuwakot districts. CGGC was the EPC contractor responsible for all civil, electro-mechanical, and hydro-mechanical works, including gradation of the 11.5 km long access road, construction of a steel bridge over Trishuli River, construction of temporary camp at headworks, and excavation of Adit no. 1 and head pond excavation. Northwest Engineering Corporation Limited (previously known as Northwest HydroConsulting Engineers) was selected as the contractor responsible for construction supervision. It was issued a supervision contract worth $4,443,926 on June 29, 2010. CGGC received a ‘Commencement of Work Order’ on June 1, 2011. The project was initiated on November 23, 2011 and it encountered various delays due to disputes over whether to build powerhouse underground or overground, disputes about whether to increase the capacity of the project, damages to the access roads leading to the project site (resulting from landslides that were triggered by an April 2015 earthquake), and a blockade imposed by India. On May 26, 2019, the first unit of the plant was successfully connected to the grid. The second unit was successfully connected to the grid later in 2019. The hydroelectric power plant was officially completed and inaugurated on November 18, 2019. The electricity that is now generated by the plant mainly serves people in Kathmandu and it reportedly fulfills seven percent of the country’s total electricity demand. There are multiple indications that the China Eximbank loan for the 60MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project has financially underperformed vis-a-vis the original expectations of the lender. In 2017, China Eximbank agreed to extend the loan's original 5 year grace period by an additional 4.5 years (increasing the total grace period to 9.5 years). This debt rescheduling is captured via Record ID#71749. Then, in 2021, China Eximbank temporarily suspended the Government of Nepal's principal and interest repayment obligations under the loan agreement for the 60MW Upper Trishuli 3A Hydroelectric Power Plant Construction Project as part of the DSSI (as captured via Record ID#104309).

Staff comments

1. The Government of Nepal’s Aid Information Management System (AMIS) records the total face value of the China Eximbank loan as $149,378,539. More specifically, it records a $97,307,324 loan commitment on February 28, 2011, a $31,934,378 loan commitment on August 17, 2011, a $3,709,001 loan commitment on September 27, 2018, a $163,803 loan commitment on December 10, 2018, a $3,113,014 loan commitment on January 15, 2019, a $6,273,096 loan commitment on June 30, 2020, and a $6,877,924 loan commitment on June 30, 2021. A detailed record of the timing and magnitude of the loan’s 58 disbursements is captured in the AMIS (https://www.dropbox.com/s/iixhtkq1krb3qa0/Feb%202023%20AMIS%20Record%20for%20Upper%20Trishuli%203A%20Hydroelectric%20Project.pdf?dl=0). 2. A report published by the Government of Nepal’s Public Debt Management Office (PDMO) puts the maturity of the loan at 9.67 years (see https://www.dropbox.com/s/2jgltrisjo9nfr1/PDMO_Annual_debt_Report_2077_1650957136.pdf?dl=0). These discrepancies warrants further investigation. 3. The Chinese project title is 上崔树里3A水电站项目 or 上崔树理3A水电站的建设. 4. The creditor's loan identification number is China Eximbank GCL[(2011)]9(359) or CHINA EXIMBANK GCL NO. (2011) 9 TOTAL NO. (1399). The Government of Nepal's debt identification number is 1399.