Overview

China Eximbank provides $143.9 million preferential buyer’s credit for Second Stage of Phase 1 of the Dushanbe-Dangara Road Reconstruction Project (Linked to Record ID#40063, #40440)

Commitments (Constant USD, 2023)$185,107,480
Commitment Year2010Country of ActivityTajikistanDirect Recipient Country of IncorporationTajikistanSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Nov 27, 2010
Start (actual)
Aug 30, 2009
End (planned)
Oct 15, 2013
End (actual)
Oct 30, 2013
First repayment (originally scheduled)
Nov 26, 2015
Last repayment (originally scheduled)
Nov 22, 2030

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project supported the reconstruction of a 50.5 km road segment along the 147.64 km Dushanbe-Vahdat-Dangara section of the Dushanbe-Kulma highway (which is also known as the Tajikistan-China highway). It also supported the construction of the 4.43 km Chormagzak Tunnel along the 147.64 km Dushanbe-Dangara section of the Dushanbe-Kulma highway. More detailed locational information can be found at https://www.google.com/maps/place/Chormaghzak+Tunnel,+Tajikistan/@38.4771348,69.1814159,17z/data=!3m1!4b1!4m5!3m4!1s0x38b66e9dde37093f:0x45059c2b6cd21c12!8m2!3d38.4771306!4d69.1836046 and https://www.openstreetmap.org/relation/180104 and https://www.carecprogram.org/uploads/TAJrev_EN.pdf

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Tajikistan Ministry of Finance

Implementing agencies

Government Agencies

  • Tajikistan Ministry of Finance

State-owned companies

  • China Road & Bridge Corporation (CRBC)

Loan description

China Eximbank provides $143.9 million preferential buyer’s credit for Second Stage of Phase 1 of the Dushanbe-Dangara Road Reconstruction Project

Grace period5 yearsGrant element53.1012%Interest rate (t₀)2%Interest typeFixed Interest RateMaturity20 years

Narrative

Full Description

Project narrative

On November 27, 2010, China Eximbank and the Ministry of Finance of the Republic of Tajikistan signed a $143,925,000 preferential buyer’s credit (PBC) agreement [China Eximbank PBC NO.2010 (025) Total No. (132)] for the Second Stage of the Phase 1 of the Dushanbe-Dangara Road Reconstruction Project. The loan carried the following borrowing terms: an interest rate of 2%, a maturity of 20 years, and a grace period of 5 years. The total project cost was $151,500,000, including a contribution of $7,575,000 from the Government of Tajikistan. The project, which was implemented in the design and construction contracting mode, involved road reconstruction, municipal road engineering, tunnels and connecting lines, etc. More specifically, the project supported the reconstruction of a 50.5 km road segment along the 147.64 km Dushanbe-Vahdat-Dangara section of the Dushanbe-Kulma highway (which is also known as the Tajikistan-China highway). It also supported the construction of the 4.43 km Chormagzak Tunnel along the 147.64 km Dushanbe-Dangara section of the Dushanbe-Kulma highway. The road repair project construction period was originally expected to last 24 months, and the tunnel and connection line construction period was originally expected to last 36 months (October 15, 2013). China Road & Bridge Corporation was awarded the implementation contract. Construction began on October 15, 2010, and ths project was completed (after passing final inspection) on October 30, 2013.

Staff comments

1. This project is linked to the China Eximbank-financed First Stage and China Eximbank-financed Third Stage of Phase 1 of the Dushanbe-Dangara Road Reconstruction Project (see Record ID#40063, #40440). China Eximbank reportedly provided $243.4 million of debt financing in total for all three stages of Phase 1. 2. The Russian project title for Stage 2 of Phase 1 is Реконструкция второго этапа Фаза I автомобильной дороги «Душанбе-Кульма» (Таджикистан – граница Китая) на участке «Душанбе - Дангара». The Chinese project title is 塔中公路一期(杜尚别—丹卡拉段)道路修复改造项目. 3. The loan agreement can be accessed via http://www.adlia.tj/show_doc.fwx?rgn=36045.