Project ID: 54624

China Eximbank provides $215 million preferential buyer’s credit for 159 km El Espino-Charagua-Boyuibe Highway Construction Project (Linked to Project ID #36350)

Commitment amount

$ 253932009.5224884

Adjusted commitment amount

$ 253932009.52

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Bolivia

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2016-12-19

Actual start

2017-06-16

Geography

Description

On December 19, 2016, China Eximbank and the Government of Bolivia signed a signed a $215,050,000 preferential buyer’s credit (PBC) agreement [China Eximbank PBC 2016 (22) 410] for the El Espino-Charagua-Boyuibe Highway Construction Project. The PBC was officially approved through the passage of a law on January 27, 2017. The law stipulates that the loan will be repaid by the General Treasury of the Nation (TGN). The PBC carries an interest rate of 3%, a maturity of 15 years, and 5 year grace period. The lender made no disbursements in 2017. It made disbursements worth $56,615,003 in 2018, $41,023,917 in 2019, $0 in 2020, and $60,425,209 in 2021. The borrower made no principal repayments between 2016 and 2021. However, it paid interest and/or fees worth $1,075,250 in 2017, $1,066,290 in 2018, $2,413,388 in 2019, an unknown amount in 2020, and $3,830,692 in 2021. The loan’s (principal) amount outstanding was $0 as of December 31, 2016, $0 as of December 31, 2017, $56,615,003 as of December 31, 2018, $97,638,920 as of December 31, 2019, $97,638,920 as of December 31, 2020, and $158,064,129 as of December 31, 2021. The project involves construction of 21 bridges, 360 sewers, 16 bus stops, 2 toll and weigh stations, 2 roundabouts in Charagua, 2 overpasses for the crossing of the railway line, and 1 viaduct, among things. The localities that will benefit from the project are Tacobo, Yaguarenda, El Espino, Guariri, Masavi, Takuru, Saipirú, Taputá, Guirapukuti, Pirití, Charagua, Machipo, Pueblo Nuevo, San Antonio de Parapetí, Ipitakuape, Itatiki, Camatindi and Boyuibe. The road will connect these localities with the city of Santa Cruz, Chuquisaca, Tarija and with the Republic of Paraguay. The contractor is China Railway Group. This 159.4 km road construction project has entered implementation. The Bolivian Highway Administration (ABC) issued an order to commence work to China Railway Group Limited on June 16, 2017. The project entered implementation at the end of 2017 and was expected to take 36 months to complete. The road was about 50% complete as of February 8, 2020. The project was delayed in 2020 due to the COVID-19 pandemic but was reactivated in mid-2021.

Additional details

1. The Spanish project title is Proyecto de Construcción Carretero 'El Espino-Charagua-Boyuibe’.

Number of official sources

18

Number of total sources

25

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Bolivia [Government Agency]

Implementing agencies [Type]

China Railway Group Limited (CREC) [State-owned Company]

Bolivia Highway Administration (ABC) [Government Agency]

Government of Bolivia [Government Agency]

Loan Details

Maturity

15 years

Interest rate

3.0%

Grace period

5 years

Grant element (OECD Grant-Equiv)

27.1264%

Bilateral loan

Export buyer's credit

Investment project loan

Preferential Buyer's Credit