Chinese Government provides RMB 377.9 million grant for Phase 2 of Low-Income Housing Project (Linked to Project ID#54795)
Commitment amount
$ 64442773.44347333
Adjusted commitment amount
$ 64442773.44
Constant 2021 USD
Summary
Funding agency [Type]
China Ministry of Commerce [Government Agency]
Recipient
Grenada
Sector
Other social infrastructure and services (Code: 160)
Flow type
Grant
Infrastructure
Yes
Category
Project lifecycle
Geography
Description
On January 20, 2017, Chinese Ambassador declared the official launch of Phase 2 of the Low-Income Housing Project in Carriacou, Grenada. The Government of Grenada secured RMB 377.9 million (EC$141.16 million) of grant funding from the Chinese Government for Phase 2 through a bilateral cooperation agreement that the two parties signed in 2015. The project’s second phase sought to provide 390 housing units in five sites in mainland Grenada and Carriacou: Frequente in St. George’s, Black Bay in St. John’s, Diamond in St. Mark’s, The Villa in St. Patrick’s and Dumfries in Carriacou, and benefit approximately 647 Grenadian families. Beijing Construction Engineering Group was the contractor responsible for project implementation. On February 1, 2017, Chinese Ambassador Ou Boqian visited the building site in St. Mark’s with Minister Clarice Modeste-Curwen of Grenada. Then, on January 26, 2018, Chinese Ambassador Zhao Yongchen attended the commencement ceremony for the project’s second phase. On December 18, 2018, construction activities at St. Patrick were completed and a topping out ceremony was held. On May 15, 2019, a groundbreaking ceremony took place at the St. George project site. On November 20, 2020, there was an official handover ceremony for the St. Patrick's project site. In April 2021, a completion ceremony at the Diamond, St. Mark's project site was held. On May 18, 2021, a completion ceremony at the project site in Dumfries in Carriacou took place. Phase 2 was originally expected to reach completion in December 2021. By the end of 2021, the project’s second phase had achieved a 100% completion rate in Diamond, St. Mark’s, a 99.9% completion rate in Corinth, St. David, a 99.9% completion rate in Beausejour, St. George, a 100% completion rate in The Villa, St. Patrick, and a 99% completion rate in Dumfries, Carriacou.
Additional details
1. This project is also known as the Second Phase of the Chinese Housing Project and the China-Aid Low-Income Housing Project Phase II. 2. In the Government of Grenada’s 2020 Estimates of Revenues and Expenditures there is a table that outlines the current status of the 5 sites.
Number of official sources
11
Number of total sources
12
Details
Cofinanced
No
Direct receiving agencies [Type]
Government of Grenada [Government Agency]