Project ID: 55590

Chinese Government provides grant for Água Grande and Mé-Zóchi Road and Drainage System Rehabilitation Project

Summary

Funding agency [Type]

Unspecified Chinese Government Institution [Government Agency]

Recipient

Sao Tome and Principe

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-01-01

Planned start

2018-01-19

Actual start

2018-03-15

Actual complete

2018-11-30

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On January 19, 2018, the Chinese Government and the Government of São Tomé and Príncipe signed an exchange of notes regarding the Água Grande District and Mé-Zóchi Road and Drainage Rehabilitation Project. The monetary value of the grant commitment for this project is unknown. The project involved the rehabilitation of 11 km of roads and 2.5 km of sewers and drains in the Água Grande District and Mé-Zóchi District. More specifically, it involved the rehabilitation of a road from Pantufo to Sam Fenícia, and a road from Riboque to Bobo Forro and Bairro do Campo de Milho (on the outskirts of the Armed Forces Headquarters). The construction of sewers and drains took place in the localities of Gonga and Sam Guembú. Top International Engineering Corporation (TIEC), which is also known as Shaanxi Construction Engineering Group Corp. LTD., was the contractor responsible for project implementation. A groundbreaking ceremony was held on March 10, 2018. However, construction did not begin until March 15, 2018. The project was completed on November 30, 2018, and officially handed over to the STP authorities on December 29, 2018.

Additional details

The Chinese project title is 的援圣多美普林西比道路整修和社区排水紧急项目. The Portuguese project title is Projeto de reabilitação de estradas, reparação de esgotos e drenagem de pântanos nos distritos de àgua Grande e Mé Zochi or Projeto de reabilitação de estradas e Sistemas de Drenagem.

Number of official sources

7

Number of total sources

11

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of São Tomé & Príncipe [Government Agency]

Implementing agencies [Type]

Top International Engineering Corporation [State-owned Company]