Chinese Government provides RMB 79 million grant for State House Construction Project

Commitments (Constant USD, 2023)$15,010,132
Commitment Year2010Country of ActivityLesothoDirect Recipient Country of IncorporationLesothoSectorGovernment And Civil SocietyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Dec 10, 2010
Start (actual)
Oct 29, 2014
End (actual)
Feb 14, 2018

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved the construction of a complex for the Office of the Prime Minister (State House) that is located in the capital city of Maseru. More detailed locational information can be found at https://www.openstreetmap.org/relation/3969601.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Lesotho

Implementing agencies

Government Agencies

  • Lesotho Office of the Prime Minister

State-owned companies

  • Anhui Construction Engineering Group

Loan desecription

Chinese Government provides RMB 79 million grant for State House Construction Project

Narrative

Full Description

Project narrative

On December 10, 2010 and December 27, 2010, the Chinese Ambassador to Lesotho and Lesotho’s Minister of Finance and Development Planning signed an exchange of letters in which the Chinese Government committed RMB 79 million of grant funding for the State House Construction Project. This project involved the construction of a complex for the Office of the Prime Minister (“State House”) that is located in the capital city of Maseru. It occupies an area of 5,320 square meters. More specifically, it involved the construction of a residence for the Prime Minister, office buildings for the Office of the Prime Minister, staff and guard houses, a helicopter landing pad, a swimming pool, gym, and a tennis court. Anhui Construction Engineering Group was the contractor responsible for implementation. It signed a project implementation contract on December 23, 2013. Construction began on October 29, 2014 and ended on February 14, 2017. The project was officially completed and handed over to the Government of Lesotho on February 14, 2018.

Staff comments

The Chinese project title is 莱索托首相府项目.