Project ID: 55696

Chinese Government provides $104 million loan for Phase I of 135MW Upper Atbara Hydropower Project

Commitment amount

$ 127907538.85949284

Adjusted commitment amount

$ 127907538.86

Constant 2021 USD

Summary

Funding agency [Type]

Unspecified Chinese Government Institution [Government Agency]

Recipient

Sudan

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

Vague (Official Finance) (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2011-03-28

Actual start

2010-05-01

Planned complete

2015-10-01

Actual complete

2018-06-11

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On April 6, 2010, China Water Power Corporation (CWE) and its parent company -- the Three Gorges Group Corporation -- formed a joint venture and signed an $838 million construction (commercial) contract with the Government of Sudan for Phase I of the the 135MW Upper Atbara Hydropower Project. Then, in 2011, the Chinese Government provided a $104 million loan to the Government of Sudan for Phase I of the the 135MW Upper Atbara Hydropower Project. The borrowing terms of the loan are unknown. The Kuwait Fund for Arab Economic Development and the Arab Fund for Economic and Social Development also provided loans of 25 million Kuwait Dinars and 50 million Kuwait Dinars, respectively, for the project. Phase I involved the creation of two dams on the Atbara and Setit rivers in Eastern Sudan with a combined capacity of 135MW. It also involved the construction of a reservoir with a storage capacity of around 3 billion cubic meters and an irrigation area of 500,000 hectares. The joint venture between China Three Gorges Corporation and its subsidiary, China National Water Resources and Hydropower Engineering Corporation, was the general contractor responsible for implementation; however, multiple subcontractors were also involved in this project Harbin Electric International Co., Ltd (HEI) assisted by implementing the electromechanical component of the project. Sinohydro 5th Bureau and the Sinohydro 7th Bureau undertook the 6,615.84-meter-long C1-B section of the project. Construction began in May 2010 and it was originally anticipated that the project would take about 65 months to finish (October 2015). Phase I of the project was ultimately completed on February 2, 2017, when the power complex began generating electricity. Then, on June 11, 2018, the last power generating unit was successfully connected to the national grid.

Additional details

1. This project is also known as the Upper Atbara Dams Complex Project. The Chinese project title is 的苏丹上阿特巴拉4×80MW水电项目 or 上阿特巴拉水利枢纽工程项目. 2. SAIS-CARI reports that the total project cost was $1.575 billion (see source ID# 64493).

Number of official sources

12

Number of total sources

17

Download the dataset

Details

Cofinanced

Yes

Cofinancing agencies [Type]

Kuwait Fund for Arab Economic Development [Government Agency]

Arab Fund for Economic and Social Development [Intergovernmental Organization]

Direct receiving agencies [Type]

Government of Sudan [Government Agency]

Implementing agencies [Type]

China Three Gorges Corporation (CTG) [State-owned Company]

SinoHydro [State-owned Company]

Harbin Electric International Co., Ltd. (HEI) [State-owned Company]

Loan Details

Bilateral loan

Investment project loan