6 Chinese medical experts support Hospital Arzobispo Loayza Expansion, paid 3 million RMB (linked to Record ID#s #73188 and #56274).

Commitments (Constant USD, 2023)$515,398
Commitment Year2012Country of ActivityPeruDirect Recipient Country of IncorporationPeruSectorHealthFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Aug 20, 2012
Start (actual)
Sep 1, 2012
End (actual)
Sep 1, 2013

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

6 Chinese medical experts to Peru assisted in the implementation of the Hospital Arzobispo Loayza expansion. More detailed locational information can be found at https://www.openstreetmap.org/way/172600382#map=18/-12.04986/-77.04462

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Peru

Implementing agencies

Government Agencies

  • Peru Ministry of Health (Ministerio de Salud) (MINSA)

Miscellaneous Agency Types

  • Arzobispo Loayza National Hospital

State-owned Banks

  • Peru Bank of the Nation (Banco de la Nación)

State-owned Policy Banks

  • China Development Bank (CDB)

Loan desecription

6 Chinese medical experts support Hospital Arzobispo Loayza Expansion, paid 3 million RMB (linked to Record ID#s #73188 and #56274).

Narrative

Full Description

Project narrative

On August 20, 2012, the Governments of China and Peru signed Letters of Exchange, in which the Chinese government committed to sending 6 Chinese experts to Peru to assist the Hospital Arzobispo Loayza Expansion Project (Project de Ampliación del Hospital Loayza). The technicians received salaries and accommodations through funds provided in the Economic and Technical Cooperation Agreement (ETCA) signed on November 23, 2009, totaling 3 million RMB. The team was expected to stay in Peru for one year, beginning at their time of arrival. While there is evidence that the they arrived in 2012, , it is unclear the exact dates of arrival and departure. The technicians included one construction expert, one water supply and drainage expert, on air conditioning experts, two electricians, and one translator-interpreter. They team both offered technical advice for the construction project and supplied additional equipment. Funds for this project were managed through the Chinese Development Bank and the Bank of the Nation of Peru (Banco de la Nación del Perú). The ETCA that funded this project provided 20 million RMB total and is captured in Record ID#73188. The construction project itself involved the addition of a General Intensive Care Unit, an Intermediate Care Unit, a Blood Bank, a Sterilization Center, and a Nutrition Center to the Archbishop Loayza National Hospital. More information can be found in Projects #56926 and #46985. If direct link to text of August 20, 2012 Letters of Exchange does not work, to access a copy, go to Derecho Internacional/dipublico.org source, CTRL+F for 3751, and download the document.

Staff comments

It is assumed that the source "Situación y Tendencias de la Cooperación Internacional en el Perú 2015" only lists five experts because it is not counting the interpreter.