Chinese Government provides grant National Stadium Access Road Construction Project (Linked to Record ID#21687, #56498, #56508, #72794)

Commitment Year2014Country of ActivityCabo VerdeDirect Recipient Country of IncorporationCabo VerdeSectorTransport And StorageFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2014
Start (actual)
Dec 15, 2014
End (planned)
Jun 1, 2015
End (actual)
Aug 31, 2015

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved the construction a 1.52 km access road (or service road) to the National Stadium (Estádio Nacional) in Praia. This road connects the stadium to the Praia City Ring Road (Anel Rodoviário da Cidade da Praia or Circular da Praia). It also involved the construction of a set of parking lots, draining culverts, and street lights at or near the site of the National Stadium. More detailed locational information can be found at https://www.openstreetmap.org/way/544648530#map=18/14.97580/-23.53012

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Cabo Verde

Implementing agencies

State-owned companies

  • China Railway 14th Bureau Group Co., Ltd. (CRCC14)

Loan description

Chinese Government provides grant National Stadium Access Road Construction Project (Linked to Record ID#21687, #56498, #56508, #72794)

Narrative

Full Description

Project narrative

In 2014, the Chinese Government and the Government of Cape Verde signed a financing agreement for the National Stadium Access Road Construction Project. This project involved the construction a 1.52 km access road (or service road) to the National Stadium (Estádio Nacional de Cabo Verde or 中国援建的佛得角国家体育场) in Praia. This road connects the stadium to the Praia City Ring Road (Anel Rodoviário da Cidade da Praia or Circular da Praia). The project also involved the construction of a set of parking lots, draining culverts, and street lights at or near the site of the National Stadium. China Railway 14th Bureau Group Co., Ltd. (中铁十四局集团有限公) was the contractor responsible for implementation. Construction began on December 15, 2014 and was originally scheduled for completion in June 2015. The project passed a quality inspection in late June 2015 and was officially handed over to the Government of Cape Verde on August 31, 2015.

Staff comments

The Chinese project title is 佛得角国家体育场场外连接道路项目. The Portuguese project title is Construção de uma estrada de Acesso or troço de ligação, por estrada, ao anel rodoviário da Cidade da Praia. According to the Government of Cape Verde, the Chinese Government provided $50 million in total via grants and interest-free loan for the construction of the National Stadium. Given that AidData has identified $20.7 million interest-free loan for Phase 1 (captured in Record ID#21687) and $15.4 million interest-free loan for Phase 2 (captured in Record ID#56498), the National Stadium Access Road Construction Project may have been supported by a $13.9 million grant. However, AidData has not yet confirmed the face value of the financial commitment for the National Stadium Access Road Construction Project. For the time being, AidData has identified this project as grant-financed.