Project ID: 57092

ICBC provides $59.58 million loan for Ndola International Airport Construction Project (Linked to Project ID#57087)

Commitment amount

$ 68656530.94891208

Adjusted commitment amount

$ 68656530.95

Constant 2021 USD

Summary

Funding agency [Type]

Industrial and Commercial Bank of China (ICBC) [State-owned Commercial Bank]

Recipient

Zambia

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

Vague (Official Finance) (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2017-01-01

Actual start

2017-10-26

Planned complete

2020-10-20

Actual complete

2021-08-05

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In November 2016, China Eximbank and the Government of Zambia signed a $337,621,439.90 preferential buyer's credit (PBC) agreement for the Ndola International Airport Construction Project (captured via Project ID#57087). The borrowing terms of the PBC are unknown. Then, in 2017, ICBC and the Government of Zambia signed a $59.58 million loan agreement for the Ndola International Airport Construction Project (captured via Project ID#57092). The borrowing terms of the ICBC loan are unknown. The proceeds of the China Eximbank PBC were to be used by the borrower to finance 85% of the cost of a $397,201,694 commercial (EPC) contract between Zambia Airports Corporation Limited (ZACL) and AVIC International Holding Corporation, which was signed on September 11, 2013 and amended on August 25, 2014. The proceeds of the ICBC loan were to be used by the borrower to finance 15% of the cost of the $397,201,694 commercial (EPC) contract between Zambia Airports Corporation Limited (ZACL) and AVIC International Holding Corporation. As of July 2022, the China Eximbank loan had achieved a 57.1% disbursement rate ($192,785,140.88 out of $337,621,439.90). The project involved the construction of a 12,000 square meter terminal building, 3 aero bridges, a 3.5 kilometer runway, a cargo terminal, a 50-room hotel, a new fire and rescue station, a cargo terminal, an aircraft maintenance hangar, and a fuel farm. AVIC International Holding Corporation was the general EPC contractor responsible for implementation. It reportedly fulfilled the government policy of having 20 percent sub-contracting to local contractors by engaging 60 local sub-contractors. 2,700 people were employed during the project construction period. A formal groundbreaking ceremony took place on June 25, 2017. However, the construction site was not handed over to the EPC contractor until September 28, 2017. The EPC contract went into effect and construction began on October 26, 2017. By December 17, 2019, the overall project had achieved a 58% completion rate; the passenger terminal completion rate was 61%, the business complex completion rate was 49%, the air traffic control building completion rate was 54%, the runway, taxiway and apron completion rate was 98%, and the viaduct completion rate was 80%. As of March 2020, the project had achieved an overall completion rate of 60%. As of April 2021, the project had achieved an overall completion rate of 88.9%. The project was originally expected to reach completion on October 20, 2020. However, due to implementation delays related to financing problems and the COVID-19 pandemic, the intended project completion date was pushed out to January 31, 2022. The airport was officially commissioned on August 5, 2021, but the airport was still reportedly waiting for operational certifications at that time. This project has also been plagued by financial problems due to overdue contractor payments. According to Clause 43.1 of the commercial contract between AVIC International Holding Corporation and ZACL, if the client (ZACL) failed to make payment within a stipulated period of time, the EPC contractor (AVIC International Holding Corporation) was entitled to the payment of interest for the late payment, which was to be calculated from the date by which the payment should have been made until the date on which payment was made by applying the interest rate as per local practice. If the payment was delayed for more than 56 days, the EPC contractor would have the right to suspend the works or terminate the commercial contract. Contrary to the clause, AVIC International Holding Corporation had not been paid a total of $97,324,668 being outstanding interim payment certificates (IPCs) for a period of more than fourteen months. In addition, there was no documentation availed to the Auditor General of Zambia to indicate why, despite the financing agreement being in force, the lender had not paid the contractor. On April 5, 2021, AVIC International Holding Corporation claimed interest on late payments on outstanding IPCs in amounts totaling $1,913,155. AVIC International Senior Consultant, Lei Yingqi, later confirmed that AVIC International Holding Corporation as an EPC contractor was using borrowed funds at high interest rates to ensure that the project continued to progress and the employees continued to be paid. He also indicated that ‘support from abroad was cut off or delayed’, which suggests that the source of the borrowed funds was not China Eximbank or ICBC. Then, on July 29, 2022, the Ministry of Finance & National Planning (MOFNP) of Zambia announced that it was seeking lender approval to formally cancel the China Eximbank loan’s undisbursed balance ($144,836,299.02); however, it also noted that it had not yet secured formal lender approval for this action. This announcement came approximately 21 months after the Government of Zambia defaulted on its repayment obligations to Eurobond holders and approximately 6 weeks after China, France, and 14 other countries formed a creditor committee to discuss the Zambian authorities’ request for a debt treatment under ‘the Common Framework for Debt Treatment beyond the DSSI’ endorsed by the G20 and the Paris Club. MOFNP also announced on July 29, 2022 that it planned to finance the completion of the Ndola International Airport Construction Project with general government revenues, and it signaled its intention to rescope the project to focus on the ‘selected works’ (i.e. access road and completion of the fuel farm).

Additional details

1. This project is also known as the Greenfield International Airport Construction Project or Simon Mwansa Kapwepwe Airport Construction Project or Copperbelt International Airport Construction Project. The Chinese project title is 赞比亚铜带国际机场建项目.

Number of official sources

15

Number of total sources

25

Download the dataset

Details

Cofinanced

Yes

Cofinancing agencies [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Direct receiving agencies [Type]

Government of Zambia [Government Agency]

Implementing agencies [Type]

Zambia Airports Corporation Ltd. [State-owned Company]

AVIC International Holding Corporation [State-owned Company]

Loan Details

Bilateral loan

Investment project loan