Project ID: 57221

Chinese Government provides RMB 159 million grant for Phase 2 of the Alto do Bandim Fishing Port Project

Commitment amount

$ 27114053.923027944

Adjusted commitment amount

$ 27114053.92

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Guinea-Bissau

Sector

Agriculture, forestry, fishing (Code: 310)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2017-07-25

Actual start

2018-10-31

Planned complete

2021-03-22

Geography

Description

After the completion of a feasibility study in April 2016, the Chinese Government and the Government of Guinea-Bissau signed a grant agreement for Phase 2 of the Alto do Bandim Fishing Port Project on July 25, 2017. China’s Ministry of Commerce was the source of funding and it committed RMB 159 million in total. Phase 1 of the Alto do Bandim Fishing Port Project was financed by the African Development Bank with US$4 million and it included the construction of a pier, a fish auction and an administrative building. Phase 2 involved the construction of a 50-meter-long floating dock, new breakwaters, administrative and fishery trade buildings, connecting roads, and drainage and sewage pipe networks within a 300-meter area. China Railway Guangzhou Engineering Group Corporation (CRGEG) was the contractor responsible for implementation. On October 31, 2018, a foundation stone laying ceremony took place. Then, on March 22, 2019, Guinea-Bissau’s Minister of Fisheries, Adiatu Djaló Nandigna, announced that Phase 2 would be completed in the next two years. However, project implementation was temporarily halted in the spring of 2020 due to the COVID-19 epidemic. Work resumed on July 15, 2020. Then, on August 10, 2020, 25,000 cubic meters of silt were successfully dredged from the port. The project has passed mid-course inspection in 12/24/2021.

Additional details

The Chinese project title is 板丁渔业码头援建项目 or 板丁渔业码头 or 援几内亚比绍板丁渔业码头项目 or 几内亚比绍板丁渔业码头 or 板丁渔业码头项目. The Portuguese project title is Segunda fase do porto de pesca do Alto do Bandim.

Number of official sources

14

Number of total sources

27

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Guinea-Bissau [Government Agency]

Implementing agencies [Type]

China Railway Guangzhou Engineering Bureau Group Co., Ltd. (CRGEC) [State-owned Company]