Project ID: 57298

Chinese Government provides grant worth 2.5 billion Comorian Francs — via November 2018 ETCA — for People's Palace Rehabilitation Project

Commitment amount

$ 6540472.830549089

Adjusted commitment amount

$ 6540472.83

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Comoros

Sector

Government and civil society (Code: 150)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-11-23

Actual start

2019-12-28

Planned complete

2020-03-28

Actual complete

2021-10-02

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On November 23, 2018, the Chinese Government and the Government of Comoros signed an Economic and Technical Cooperation Agreement (ECTA), which committed grant funding worth 1.3 billion Comorian Francs for the People's Palace Rehabilitation Project. However, by 2019 (when project implementation commenced), the size of the Chinese Government’s grant commitment for the People's Palace Rehabilitation Project had apparently increased to 2.5 billion Comorian Francs. The purpose of the project was to renovate the internal and external surfaces of the People’s Palace, its hallway, office area, performance hall, and outdoor facilities. It also sought to add new spaces to the complex. The total floor area to be renovated was 4460 square meters. The People's Palace houses the Comorian legislative assembly and was initially built with substantial Chinese aid in 1980. China Qiyuan Engineering Cooperation and Zhongding International Construction Group were the contractors responsible for the rehabilitation project. A groundbreaking ceremony took place on December 28, 2019 and project was originally expected to take 15 months to complete (March 28, 2020). On July 22, 2021, the rehabilitation project successfully passed a final inspection conducted by a team of experts from China’s Ministry of Commerce (MOFCOM). Then, on October 2, 2021, an opening ceremony was held for the renovated People's Palace.

Additional details

1. The The French project title is Réhabilitation du Palais du peuple. The Chinese project title is 援科摩罗人民宫修缮项目.

Number of official sources

12

Number of total sources

20

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Comoros [Government Agency]

Implementing agencies [Type]

China Qiyuan Engineering Cooperation [NGO/CSO/Foundation]

Zhongding International Engineering Co., Ltd. (ZIEC) [State-owned Company]