Project ID: 57537

Chinese Government provides grant for Gorongosa Technical Institute Construction Project (Linked to project ID#66213)

Commitment amount

$ 13078196.974544121

Adjusted commitment amount

$ 13078196.97

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Mozambique

Sector

Education (Code: 110)

Flow type

Grant

Infrastructure

No

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-01-01

Planned start

2018-06-04

Actual start

2019-07-31

Planned complete

2020-01-31

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On June 4, 2018, the Chinese Government and the Government of Mozambique signed a USD $12 million grant agreement for the Gorongosa Technical Institute Construction Project. This agreement was one of five agreements signed at this time within the framework of the Joint Commission for Economic, Technical and Commercial Cooperation between the two countries (recorded in the umbrella project ID#66213). This project involves the construction of the Gorongosa Technical Institute in Sofala Province. It includes construction of teaching buildings, workshops, a cafeteria, dormitories for students, and apartments for teachers. Upon completion, it is expected that the institute will have capacity to train 740 students each year and offer courses in agriculture and livestock production, agricultural extension, and agro-processing. In addition to a boarding school, the project includes a testing ground and sports infrastructure. China National Nuclear Corporation is the contractor responsible for project implementation. A groundbreaking ceremony was held on July 31, 2019. As of May 25, 2020, this project had achieved a 46.56% completion rate, with the pandemic having caused a delay in the implementation of the project. The work was projected to last 18 months, with classes expected to start in the academic year of 2021. As of September 2021, the project was thought to still be in the implementation stage.

Additional details

The Chinese project title is 索法拉职业技术学校 or 索法拉职业技术学校项目. The Portuguese project title is Construção do Instituto Técnico de Gorongosa em Sofala or Projeto de apoio do instituto médio politécnico de Gorongosa.

Number of official sources

7

Number of total sources

17

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Mozambique [Government Agency]

Implementing agencies [Type]

China National Nuclear Corporation (CNNC) [State-owned Company]